| |
Decision CRTC 2001-23
|
| |
Ottawa, 25 January 2001
|
| |
Ledcor/Vancouver – Construction, operation and maintenance of
transmission lines in Vancouver
|
| |
Reference:
8690-C12-01/99
|
| |
This proceeding arose as a result of a disagreement between the
City of Vancouver (Vancouver) and Ledcor Industries Limited (Ledcor)
relating to the terms and conditions under which Vancouver would
grant Ledcor consent to construct a fibre optic transmission system
in Vancouver.
|
| |
In this majority decision, the Commission is resolving the
dispute between Vancouver and Ledcor. The Commission is granting
permission to Ledcor to construct, maintain and operate transmission
lines that Ledcor has constructed in 18 street crossings in
Vancouver, and is prescribing terms and conditions related to that
permission.
|
| |
Background
|
| |
Initial applications
|
|
1. |
On 19 March 1999, Ledcor Industries Limited filed a Part VII
application requesting relief pursuant to sections 43 and 61(2)
of the Telecommunications Act (the Act), naming the City of
Vancouver (Vancouver) as respondent. Ledcor requested that the
Commission issue interim and final orders granting it, its affiliate
(Worldwide Fiber (F.O.T.S.) Ltd.), and its customers permission to
access street crossings and other municipal property in Vancouver to
install, operate and maintain Ledcor's fibre optic transmission
lines. Ledcor stated that it had not been able to obtain the
consent of Vancouver, required by section 43 of the Act, for access
to the street crossings and other municipal property on terms
acceptable to it. |
|
2. |
Ledcor stated that Vancouver had proposed a number of conditions
for granting access that Ledcor found unacceptable,
including:
|
| |
a) distance-based access (licence) fees that far exceed the costs
of providing access;
|
| |
b) additional licence fees that would require Ledcor to pay
Vancouver a share of its telecommunications revenues in
Vancouver;
|
| |
c) a requirement to give Vancouver exclusive use of four fibre
strands on its fibre optic system in the Vancouver
area; |
| |
d) a requirement that Ledcor provide Vancouver with information
on its customers, in order that Vancouver could impose additional
revenue-sharing licence fees on Canadian carriers that had purchased
fibres, indefeasible rights of use (IRUs), or similar capacity on
its fibre optic system; and |
| |
e) numerous other restrictions and requirements that were far
more costly and onerous than those imposed by other municipalities,
railways and other property owners with which Ledcor had
successfully negotiated access agreements.
|
|
3. |
With its application, Ledcor provided copies of the Municipal
Access Agreement (MAA) and Street Crossing Agreement (SCA) advanced
by Vancouver during the negotiations. |
|
4. |
Ledcor stated that it had continued to construct its fibre optic
system, including segments of the system located in Vancouver, while
discussions with the city had proceeded. |
|
5. |
In a ruling dated 8 April 1999, the Commission denied a request
from Vancouver to suspend Ledcor's application pending disposition
of an application to be filed by the city. The Commission noted that
the two applications would, in essence, raise the same issues,
namely, the terms and conditions of access to municipal property in
Vancouver for the purpose of constructing, maintaining and operating
transmission lines. The Commission concluded that it would be in the
public interest to deal with both applications concurrently. The
Commission also stated that, following closure of the record on the
two applications, it would issue a public notice initiating a
proceeding to consider the issues raised. |
|
6. |
Pursuant to the Commission's ruling of 8 April 1999,
Vancouver filed a Part VII application on 17 May 1999. In its
application, Vancouver stated that Ledcor had constructed a fibre
cable in the city's streets without obtaining the city's consent or
permission. Vancouver further stated that, according to press
reports, strands on this cable had been acquired by MetroNet
Communications Group Inc., Call-Net Enterprises Inc., Bell Canada
and Canadian Pacific Railway (CPR), while BCT.TELUS Communications
Inc. (TELUS) had either already acquired strands or was in
negotiations to acquire strands. Vancouver named TELUS, Call-Net and
Bell Canada as respondents to its application, stating that none of
these carriers had obtained the city's consent or permission prior
to taking ownership of the fibre, or permitting Ledcor to install it
on their behalf. |
|
7. |
Vancouver requested an order to establish the terms and
conditions of access by the respondents to street crossings and
other municipal property to construct, maintain and operate
transmission facilities. Vancouver also requested that the
Commission make an interim order for a zero rate of consideration,
to enable the Commission to make its final order in this matter take
effect on the date of the interim order. |
|
8. |
On 27 October 1999, the Commission granted Vancouver's request
for an interim order, pending its final determination. The
Commission ordered, as a condition of access, that each of the
respondents forthwith pay $1 to Vancouver. |
| |
Initiation of the proceeding |
|
9. |
On 3 December 1999, the Commission issued Terms and conditions
for access to municipal property in the City of Vancouver,
Telecom Public Notice CRTC 99-25,
to consider the appropriate terms and conditions of access by
Canadian carriers and distribution undertakings (collectively,
"carriers") to municipal property in Vancouver for the purpose of
constructing, maintaining and operating transmission lines. The
Commission stated that, while the proceeding would be limited to the
terms and conditions of access in Vancouver, it expected that the
principles developed in the proceeding may inform the Commission's
consideration of any disputes that may arise
elsewhere.
|
|
10. |
In PN 99-25,
the Commission invited parties to comment on: (a) the scope and
nature of the Commission's jurisdiction to set the terms and
conditions of access in light of sections 42 to 44 of the Act, and
any other provisions of the Act that may be relevant; (b) the terms
and conditions, including whether some form of monetary compensation
could and should be ordered as a condition of access; (c) what form
any monetary compensation should take, including submissions as to
costing methodology; and (d) whether any terms and conditions
imposed by the Commission in relation to the agreements for access
in Vancouver that are in dispute could and should replace the terms
and conditions in existing agreements that are not in dispute,
relating to municipal access in Vancouver.
|
|
11. |
Ledcor, Vancouver, TELUS, Call-Net, Bell Canada, AT&T
Telecom Services Company Inc., GT Group Telecom Services Corp.
(Group Telecom), BC TEL, and all affiliates of these entities that
are Canadian carriers with any part of their transmission facility
located on municipal property within Vancouver, were made parties to
the proceeding. |
|
12. |
Pursuant to the procedure established in PN 99-25,
the following parties filed submissions on 28 January 2000:
Alberta Urban Municipalities Association; Bell Canada and MTS
Communications Inc.; City of Calgary (Calgary); Call-Net; Canadian
Cable Television Association (CCTA); Canadian Institute of Public
and Private Real Estate Companies and Building Owners and Managers
Association; City of Edmonton (Edmonton); Federation of Canadian
Municipalities (FCM); Halifax Regional Municipality (HRM); Ledcor;
Regional Municipality of Ottawa Carleton (RMOC); Corporation of the
City of New Westminster and the City of Richmond (New
Westminster/Richmond); TELUS; City of Toronto (Toronto) and
Vancouver.
|
|
13. |
Interrogatories were addressed to those filing submissions on 28
February 2000, and responses were filed on 29 March
2000. |
|
14. |
On 5 June 2000, the Commission issued a letter ruling on requests
for further responses to interrogatories and for disclosure of
information filed under claim of confidence. In addition, the
Commission addressed supplemental interrogatories to Vancouver and
set out the procedure for the rest of the
proceeding. |
|
15. |
Vancouver filed its responses to the Commission's supplemental
interrogatories on 17 July 2000. |
|
16. |
On 14 August 2000, the following parties filed comments: AT&T
Canada Corp.; Bell Canada/MTS; Calgary; Call-Net; CCTA;
Edmonton; FCM; Futureway Communications Inc.; Group Telecom; New
Westminster/Richmond; RMOC; TELUS; Toronto; WFI Urbanlink Ltd. and
Ledcor and Vancouver. |
|
17. |
The Commission also received 33 letters, primarily from
municipalities and counties, essentially expressing support for the
Rights-of-Way Principles advanced by FCM in the
proceeding. |
|
18. |
On 5 September 2000, the following parties filed replies:
AT&T Canada; Bell Canada/MTS; Calgary; Call-Net; CCTA; Edmonton;
FCM; HRM; Ledcor; RMOC; TELUS; Toronto and
Vancouver. |
|
19. |
At pages 1 and 2 of its reply in this proceeding, FCM submitted
that, in the comment phase, certain carriers introduced new
allegations contrary to municipal interests. FCM stated that these
carriers could have provided evidence as to these allegations in
their initial submissions of 28 January 2000. FCM submitted
that it is not able to respond to these allegations on the basis
that the procedure established for this proceeding does not allow
FCM to obtain particulars or to test the allegations. Accordingly,
FCM submitted that it would be inappropriate for the Commission to
take any such allegations into account in rendering its
decision. |
|
20. |
The Commission notes with respect to FCM's objections that it has
not taken the allegations in question into account in rendering this
decision, as they are not relevant to the issues being
determined. |
| |
Vancouver's proposal |
|
21. |
In its submission of 28 January 2000, Vancouver argued that
competition in the communications industry is making space in
municipal streets an increasingly scarce societal resource. In
addition, other uses (electricity, gas, storm and sanitary sewers,
underground malls, etc.) increase the demand for space
allocation. |
|
22. |
Vancouver stated that, in a monopoly environment, access to
public property was accorded on a first-come, first-served basis. In
such an environment, the subscriber base to a utility service such
as telephony was virtually identical to the taxpayer base.
Therefore, the exercise of allocating costs to cost-causers was
scarcely justified, since the result would be merely to transfer
cost from one bill to another in a virtually identical customer
base. |
|
23. |
Vancouver submitted that, in the current competitive environment,
a carrier's customer base and the taxpayer base are no longer the
same, and the previous regime no longer makes sense. It further
submitted that the most efficient way to allocate such a scarce
resource is to assign the full costs of the resource to the
cost-causer. In this way, users of public property will have an
incentive to make as efficient use as possible of public property,
and those applications that are of the greatest societal benefit
will be more likely to achieve access to public
property. |
|
24. |
Vancouver argued further that, when public property is scarce and
has market value, it is equitable that the owner be compensated for
its use by others in proportion to its value to others; to do
otherwise would be to subsidize users, such as carriers and their
shareholders and customers, at the expense of the city and its
taxpayers. |
|
25. |
Vancouver proposed that it recover all costs causally incurred by
it as a result of the use and occupation of its public property by
carriers. Vancouver submitted that there are a variety of one-time
and on-going causal costs incurred by the city due to the presence
or placement of telecommunications plant in its streets. Vancouver
proposed to recover one-time costs through up-front charges based on
actual incurred or estimated costs. This category would include
costs for the approval of applications and plans, inspections, costs
of transit delays due to construction, lost parking meter revenues,
pavement restoration, etc. Vancouver proposed to recover on-going
costs through annual linear charges (per metre of transmission
line). This category would include costs of pavement degradation due
to cuts during the construction of transmission facilities, and lost
productivity in the city's own operations in street resurfacing and
in sewer and waterworks construction, etc., due to the presence of
transmission facilities in the street. |
|
26. |
In addition to the above, Vancouver proposed an annual linear
"land" charge, based on the value of adjacent
lands. |
|
27. |
Vancouver also proposed to apply to its direct and indirect
costs: (a) a "multiplicative factor" to recover variable common
costs, and (b) a contribution to fixed and common costs at a
suggested rate of 25%. These two factors would apply to all but the
annual linear land charge. |
|
28. |
Vancouver also proposed, among other things, that carriers be
responsible for the full cost of relocating their facilities,
whenever such relocation was required for bona fide municipal
purposes (including municipal beautification programs). As well,
Vancouver maintained that it should not be held liable for damage to
the plant of carriers and distribution undertakings resulting from
municipal operations in the street. |
|
29. |
Vancouver also argued that only the city has the resources and
expertise to co-ordinate the various requirements for, and uses of,
rights-of-way. Vancouver submitted that it should be given the
ability "to facilitate greater co-ordination among the various
carriers that locate in the street." In this context, it stated that
it must have the ability (a) to require carriers to provide extra
duct capacity when the street is dug up initially; and (b) to
require this extra capacity and other third party duct capacity to
be used by other carriers wanting to use the same
alignments. |
|
30. |
Vancouver argued that confirming its mandate to facilitate
sharing and co-ordination would not only maximize the efficient use
of crowded municipal property, but would also minimize duplication
of effort and costs (e.g., cuts to municipal pavement would be
reduced, road surfaces would last longer, and disruptions to the
public, business and municipal works would be
decreased). |
|
31. |
The Commission notes that Vancouver's submission of 28 January
2000 made no mention of the provision of dark fibre or percentage of
revenue fees. In response to interrogatory Vancouver(CRTC)28Feb00-2,
Vancouver confirmed that its January submission constituted the
entirety of its proposal, and that the quantum of payment required
from carriers in Vancouver would be based on the costing methodology
it proposed. However, Vancouver added that, once the quantum is
established, the form of compensation should be freely negotiated
between the parties. Vancouver submitted that some carriers prefer
payment to be in the form of percentage of revenue fees or the
provision of dark fibre. |
| |
The Commission's jurisdiction and the scope of the Commission's
decision |
| |
Municipal consent |
|
32. |
In the following section, the Commission addresses its
constitutional and statutory jurisdiction. It is important to note
at the outset that Parliament has provided in section 43(3) of the
Act that "no Canadian carrier or distribution undertaking shall
construct a transmission line on, over, under or along a highway or
other public place without the consent of the municipality or other
public authority having jurisdiction over the highway or other
public place". Where carriers cannot obtain the consent of the
municipality or other public authority (the "municipality") on
acceptable terms, they may apply to the Commission for permission
pursuant to section 43(4) of the Act. In addition, municipalities
can apply to the Commission to settle disputes under section 44 of
the Act. |
| |
The Commission's jurisdiction |
|
33. |
With respect to constitutional jurisdiction, municipalities
argued that the Commission should only intervene pursuant to
sections 42 to 44 of the Act to the extent that the actions of a
municipality are sterilizing a vital part of a federal undertaking.
This argument is not supported by the applicable constitutional
principles. The entering on and breaking up of any highway or other
public place by a carrier for the purpose of constructing,
maintaining or operating its transmission lines is subject to
exclusive federal constitutional
jurisdiction. |
|
34. |
In the Commission's view, sections 43 and 44, and this decision,
relate in pith and substance to telecommunications. Any effects on
property and civil rights in the province are incidental. All
matters that are a vital part of the operation of a federal
undertaking are within the exclusive legislative control of
Parliament. Whether to construct and where to construct transmission
lines (a vital part of a telecommunications undertaking) are matters
of exclusive federal concern, as are the design of the transmission
lines, the material to be incorporated and other similar
specifications. All terms and conditions that will be permanently
reflected in the structure of the transmission lines, or have a
direct effect on the operational qualities of the transmission
lines, are within exclusive federal jurisdiction. Finally, the use
of property (such as a municipal highway) for the purposes of a
transmission line cannot be divorced from the exclusive federal
constitutional jurisdiction over
telecommunications. |
|
35. |
In the Commission's view, the Act sets out a detailed statutory
code with respect to construction issues involving carriers and
municipalities. In establishing this framework, Parliament has
required that consent be obtained by carriers from such authorities,
but has recognized that carriers may not be able to obtain that
consent on acceptable terms. It has therefore provided mechanisms
for the Commission to resolve disputes regarding appropriate terms
and conditions. |
|
36. |
During this proceeding, carriers asserted that they have an
independent statutory right to enter on and break up a highway for
the purpose of constructing, maintaining or operating their
transmission lines. In the Commission's view, the Act provides
carriers a qualified right to enter on and break up highways for
these purposes, i.e., subject to not unduly interfering with the
public use and enjoyment of the highway and to the requirement for
municipal consent (or the permission of the
Commission). |
|
37. |
Carriers also argued that sections 43 and 44 do not create
additional powers for municipalities beyond those that they would
otherwise have. They further submitted that the Commission can do no
more under subsection 43(4) than a municipality could do under
subsection 43(3). Subsection 43(4) provides that, where consent on
acceptable terms has not been obtained from a municipality, the
Commission may grant the permission "subject to any conditions that
the Commission determines". The only qualification in the subsection
is that the Commission must have due regard to the use and enjoyment
of the highway or other public place by others. The carriers'
argument is untenable. The statute clearly provides the Commission
full discretion to determine the
conditions.
|
|
38. |
Carriers submitted that the Commission's authority under sections
43 and 44 for access charges is limited to ensuring that such
charges are subject to the concurrence of the carrier and recover
only clearly identified direct out-of-pocket expenses. As noted
above, subsection 43(4) provides that, where a carrier cannot obtain
the consent of the municipality on acceptable terms, the carrier may
apply to the Commission, and the Commission "may, having due regard
to the use and enjoyment of the highway or other public place by
others, grant the permission subject to any conditions that the
Commission determines" (emphasis added). In the Commission's
view, this phrase is sufficiently broad to include conditions as to
compensation (costs and otherwise). Carriers further argued that a
series of older decisions, by various bodies, determine that the
Commission cannot in this proceeding make compensation a condition
of its order. In the Commission's view, however, these cases are not
determinative of the issues at hand. In any event, in addition to
the possibility of jurisdiction with respect to compensatory
conditions being located in sections 43 and 44 themselves, section
42 explicitly gives the Commission jurisdiction to make conditions
relating to compensation. The suggestion that the scope of section
42 is somehow limited to the scope of the powers under sections 43
and 44 (if in fact these sections do not support conditions as to
compensation in and of themselves) is also to be rejected. Such a
suggestion is contrary to the very purpose of section 42, which is
to complement powers that the Commission has under other
provisions. |
|
39. |
Municipalities also raised the question of expropriation. In the
Commission's view, this decision does not give rise to
expropriation. Rather, it forms part of a valid regulatory scheme
that relates in pith and substance to
telecommunications. |
| |
The Commission's decision |
|
40. |
During the course of the proceeding, several parties urged the
Commission to establish clear principles governing the terms and
conditions under which carriers may be granted access to public
property for the purposes of constructing, maintaining and operating
transmission lines. Some urged the Commission to adopt a standard
"template" agreement with respect to such access. |
|
41. |
Other parties, notably Toronto, argued that the Commission has no
jurisdiction to rule on terms and conditions of access to public
property for these purposes with respect to non-parties to the
proceeding, or on anything other than the actual dispute before
it. |
|
42. |
In this decision, the Commission, by majority, is granting Ledcor
permission to construct, maintain and operate transmission lines in
18 street crossings in Vancouver, and is establishing terms and
conditions related to that permission. In light of the Commission's
conclusions with respect to Third party issues (see below),
the relief sought by Vancouver against the respondents to its
initial application is not required or appropriate; nor is the
municipality's consent or the Commission's permission necessary for
the mere presence of Ledcor's transmission lines in the conduit of
another carrier, such as TELUS. |
|
43. |
With regard to any future activities (excavation, installing
fibre, etc.) that Ledcor may undertake in relation to the
transmission lines in the 18 street crossings, the Commission
considers that the requirement to obtain consent from Vancouver
should be related to Ledcor's obligation to ensure that there is no
undue interference "with the public use and enjoyment of the highway
or other public place." Therefore, where Ledcor's activities would
entail disruption (for example, if excavation or a disruption to
traffic is involved), it is to obtain Vancouver's consent for those
activities. However, the Commission considers that there is no
requirement for prior written consent for excavation or other
disruption in the case of an emergency, provided that Ledcor
notifies Vancouver as soon as possible of the emergency and of
Ledcor's activities in respect of it. In such instances, if
excavation is involved, Ledcor should restore the surface to its
original condition, or as close as possible to its original
condition, to the reasonable satisfaction of Vancouver (see
Pavement restoration, below). |
|
44. |
The Commission is not, in this decision, prescribing terms and
conditions related to the future construction by Ledcor, or any
other carrier, of transmission lines in Vancouver or elsewhere.
However, the Commission has developed principles, as set out in this
decision, in addressing the dispute currently before it. The
Commission anticipates that these principles will also assist
carriers and municipalities in negotiating the terms and conditions
under which municipalities will grant carriers consent to construct,
maintain and operate transmission lines on or in municipal property,
without having to resort to an application pursuant to section 43 or
44. The Commission is not persuaded that it is appropriate for it to
adopt any particular model or standard agreement to serve as a
starting point for discussions between municipalities and
carriers. |
|
45. |
Section 47 of the Act requires the Commission to exercise its
powers and perform its duties with a view to implementing the
Canadian telecommunications policy objectives set out in section 7
of the Act. Section 43(4) of the Act specifies that the Commission
may grant permission for a carrier to construct transmission lines,
subject to any conditions that the Commission determines, having due
regard to the use and enjoyment of the highway or other public place
by others. Accordingly, in rendering this decision, the Commission
has considered the policy objectives set out in section 7 of the
Act, while taking into account the concerns of municipalities and
others.
|
|
46. |
The Commission notes, as argued by Group Telecom, that
greater demand for rights-of-way derives from a competitive
telecommunications market and the expanded roll-out of modern,
high-speed networks. The benefits of a competitive
telecommunications market and greater access to modern, high-speed
networks are not enjoyed solely by the shareholders and customers of
carriers. The economic base that such facilities support will
provide generalized benefits throughout the municipality, attracting
industry, creating jobs, increasing tax revenue,
etc. |
| |
Joint planning issues |
| |
The importance of joint planning |
|
47. |
Vancouver argued that an important dimension of its stewardship
of public property is its ability to encourage sharing and
co-ordination, not only among competing carriers, but all present
and future users of public property. |
|
48. |
Bell Canada/MTS proposed that the Commission strongly encourage
municipalities and users of municipal rights-of-way to enter into
co-operative joint planning and co-ordination arrangements. Several
carriers submitted that many, if not most, of the concerns
identified by Vancouver regarding the alleged impacts upon road
construction and maintenance costs could be substantially addressed
through the establishment of improved joint planning processes
between municipalities and users of municipal
rights-of-way. |
|
49. |
Bell Canada/MTS provided a template outline of the mandate, goals
and structure of a typical Public Utility Coordinating Committee
(PUCC). The template described the activities of such a committee
as: (1) communication; (2) co-ordination of projects and capital
works plans (with a requirement for all members to provide long
range plans for major capital works, road modification, paving
programs, and major maintenance programs); (3) standardization
(including the development of standards and specifications for joint
infrastructure builds); (4) damage prevention; (5) resolution
of conflicts; and (6) development of an integrated mapping
system. |
|
50. |
In reply, Vancouver stated that it is moving to set up a
co-ordinating committee. However, Vancouver, other municipalities
and FCM expressed the view that joint planning alone could not
address all municipal rights-of-way management
issues. |
|
51. |
The Commission recognizes that municipalities have an important
role to play in the co-ordination of all parties seeking to occupy
and use municipal rights-of-way, especially the larger
municipalities whose downtown cores are experiencing the highest
demand for space. In particular, the Commission agrees with those
carriers who advocated increased reliance on joint planning and
co-ordination arrangements such as PUCCs, involving all users of
municipal rights-of-way, not just carriers. |
|
52. |
The Commission notes the submissions of municipalities that
improved joint planning is not a "panacea". Nonetheless, the
Commission agrees with parties who argued that the joint planning
and co-ordination process could help to minimize many of the
concerns raised by Vancouver, other municipalities and FCM regarding
excessive road cuts, pavement degradation, congestion, need for
relocations, potential liability, etc. |
|
53. |
Among other things, the Commission considers that a PUCC or
similar body (a) would provide the municipality with a forum to
announce its long range plans as to road construction and
maintenance, affording carriers and other users an opportunity to
co-ordinate their construction plans with those of the municipality;
(b) could set up a communications process to advise all carriers
that a particular carrier is installing duct structure or other
buried facilities; and (c) could provide a mechanism for carriers to
exchange information as to the availability of spare
capacity. |
|
54. |
The Commission expects carriers to participate in joint planning
and co-ordination committees, such as the one discussed by Bell
Canada/MTS, in municipalities in which they have, or plan to have, a
significant presence. The Commission also expects that carriers will
be able, in the context of such committees, to exchange information
at a sufficient level of detail to facilitate the co-ordination
process, without compromising competitively crucial information.
Finally, the Commission would consider it reasonable for carriers to
contribute to the costs of any such committees. |
|
55. |
The Commission does not consider it necessary to adopt Group
Telecom's approach and establish a task force to consider whether
PUCCs could be made more effective or whether the operations of the
most effective PUCCs might serve as a model for PUCCs
elsewhere. |
| |
Extra duct capacity |
|
56. |
In its submission of January 2000, Vancouver stated
that it must have the ability (a) to require carriers
to provide extra duct capacity when the street
is dug up initially; and (b) to require this extra
capacity and other third party duct capacity to
be used by other carriers wanting to use the same
alignments. In response to interrogatory Vancouver(CRTC)28Feb00-3
PN 99-25,
Vancouver stated that the amount and allocation of extra capacity
would be determined jointly by carriers and the
city.
|
|
57. |
Several carriers commented that all carriers will provision, as a
matter of course, duct capacity which is designed to meet their
future needs. Thus, it is most certainly the case that carriers will
provision duct space which is surplus to their current needs. They
added that a mandated requirement to provision capacity that is
materially in excess of that required in the future by all carriers
will impose costs on carriers that cannot be
recovered. |
|
58. |
The Commission accepts the submissions of municipalities that the
demand for space in rights-of-way in downtown core areas of major
urban centres is likely to increase. The Commission therefore
encourages the sharing of facilities and support structures to the
greatest extent possible in such areas. However, the Commission does
not consider it appropriate that municipalities impose on carriers a
requirement to construct capacity beyond their needs, or require
other carriers to use this capacity rather than constructing their
own facilities. In the Commission's view, Vancouver's proposal of
28 January 2000 would intrude on areas under the Commission's
jurisdiction, would improperly affect a "vital part" of the federal
undertaking, and would (as argued by TELUS) add another layer of
regulation to the question of access to support
structures. |
| |
Vancouver's costing proposal |
| |
General |
|
59. |
In its submission of 28 January 2000, Vancouver proposed that it
recover all costs causally incurred by it as a result of the use and
occupation of its public property by carriers. |
|
60. |
Vancouver asserted that its specific costing proposals were based
on Phase II costing principles, initially established in Phase II
of the cost inquiry, Telecom Decision CRTC 79-16, dated 28
August 1979. The city also stated (in response to interrogatory
Vancouver (Bell/MTS)28Feb00-10) that it had adopted the philosophy
set out at page 28 of the Bell Canada Phase II costing manual that
"the cost and effort expended on the cost estimation activity should
be commensurate with the size and significance of the
study." |
|
61. |
The Commission notes that, for costs to be included under Phase
II principles, they must be prospective (i.e., forward-looking, in
that "sunk" costs are not included) and incremental (i.e., only
costs that change as a result of the project are considered). These
prospective incremental costs are referred to as causal costs. The
Commission considers it appropriate that Vancouver recover the
causal costs it incurs when carriers construct, maintain and operate
transmission lines in municipal rights-of-way. |
|
62. |
In its second revised response to interrogatory
Vancouver(Bell/MTS)28Jan00-6, Vancouver applied its costing proposal
to an example of a construction project in its downtown core to
derive the charges that would apply. In calculating these charges
Vancouver estimated its direct costs, and then applied a 62% loading
to take into account indirect costs, variable common costs and fixed
common costs. The specific loading for fixed common costs was
25%. |
|
63. |
The Commission notes that fixed costs, by definition, do not vary
with a particular project. Thus, they are not incremental costs, as
defined above. The Commission has allowed telephone companies to
include a mark-up on their Phase II costs, representing a
contribution to fixed common costs, in the prices they charge for
their services. A municipality differs from a business in that it
derives its revenues primarily from taxes, and the fixed common
costs of running the municipality are appropriately covered by this
tax revenue. Therefore, the Commission considers that fixed common
costs should not be recovered through charges to carriers.
Accordingly, the Commission considers it appropriate to exclude the
25% component for the recovery of fixed common costs from
Vancouver's proposed 62% loading. The Commission finds acceptable
Vancouver's proposed 29.6% loading on direct costs to estimate
indirect and variable common costs. |
|
64. |
For some of Vancouver's cost elements, the causal costs are small
and the process to determine them accurately would be
disproportionately difficult or complex. The Commission considers it
appropriate to recognize such costs by way of a further 15% loading
on plan approval and inspection costs, which can be more readily
estimated. |
|
65. |
The various types of costs that Vancouver proposed to recover are
examined below with regard to the above costing
principles. |
| |
Elements of the proposal |
| |
a) Plan approval and inspection costs |
|
66. |
Vancouver submitted that costs relating to plan approval and
inspections depend on the number of plans received and the length of
the plant installed. Vancouver calculated a base cost of $230 for
projects of 20 metres or less, and a base cost of $760 plus a base
per-metre cost of $6 for projects in excess of 20 metres. Vancouver
proposed to apply its 62% loading to these costs to arrive at the
applicable charges. |
|
67. |
The Commission agrees that plan approval and inspection costs are
causal to the specific construction project. |
|
68. |
The Commission notes that Vancouver's proposed fee structure is
based on the premise that project approval and inspection is less
complex for projects not requiring plant installations greater than
20 metres. The Commission considers it reasonable that there be a
distinction between simple and complex projects. While using the
trench length of 20 metres as the delineation between simple and
complex projects may be somewhat arbitrary, it has the advantage of
administrative simplicity. The Commission also notes Vancouver's
submission that approvals for projects of 20 metres or less do not
require all of the activities necessary for larger projects (for
example, inspections). |
|
69. |
The Commission therefore finds Vancouver's proposed fee structure
reasonable, but considers that the level of the fees should be
adjusted. First, as noted above, the Commission considers that the
25% loading for fixed common costs should be removed. Second, as
noted above and discussed further below, the Commission considers
that there are costs associated with the construction process that
could be disproportionately difficult or costly to estimate with
reasonable accuracy, such as (a) net revenue losses when parking
meters are put out of service; and (b) costs associated with transit
operating delays. The Commission considers that these costs should
be recognized through a 15% loading on the plan approval and
inspection costs. Should the municipality be able to estimate these
costs with reasonable accuracy, the Commission would consider it
appropriate to include them explicitly. |
|
70. |
In the case of Vancouver, when the 25% loading for fixed common
costs is removed and the 15% loading is added, the applicable
charges for plan approvals and inspections are: (a) a flat fee of
$341.55 for a project of 20 metres or less; and (b) for
projects in excess of 20 metres, a flat fee of $1,127, plus a per
metre charge of $8.67. |
|
71. |
With regard to the distance-based component of the above charges,
the Commission notes that Vancouver also proposed an annual
per-metre charge intended to recover the market-based value of the
land occupied by carriers in municipal rights-of-way. As discussed
below, the Commission considers such charges inappropriate. The
Commission notes that any distance-based plan approval and
inspection charges must be causally related to the plan approval and
inspection process. |
|
72. |
As discussed above, the Commission encourages Vancouver, and
other municipalities, to establish utility co-ordinating committees,
involving the municipality and all users of rights-of-way. The
Commission would consider it appropriate that carriers contribute to
the costs of any such committees. In addition, the Commission
considers that the activities of such committees would likely reduce
the causal costs that municipalities would otherwise incur in the
plan approval and inspection process. |
| |
b) Construction disruption costs |
| |
(i) Traffic signing costs |
|
73. |
Vancouver stated that it incurs traffic signing costs to clear
parking in areas affected by construction, etc. (e.g., to hood
traffic meters and post related signage). The Commission considers
that these one-time costs are causal to the project and that
Vancouver should recover them from the carrier. |
| |
(ii) Parking meter revenue |
|
74. |
Vancouver indicated that, when parking meters are taken out of
service due to construction, it loses revenue that would otherwise
have been deposited in the meters. |
|
75. |
Vancouver submitted that the amount of lost revenue is dependent
on the hourly rate charged, which varies across the city, and the
percentage utilization of the available parking meter
time. |
|
76. |
Vancouver proposed that carriers such as Ledcor be billed
directly for this lost revenue, at the time the construction work
takes place. Vancouver submitted that it does not currently charge
utility companies for this lost revenue, but does charge moving
companies, construction companies, film companies and others that
require clearance of parking. |
|
77. |
For its example construction project, Vancouver calculated an
applicable charge of $27,631. |
|
78. |
While the Commission expects that the city would experience some
loss of revenue when parking meters are taken out of service, a
reasonable estimate of the causal impact must represent the net
loss, and not the gross loss. The base cost calculated by Vancouver
in its example represented the gross loss. |
|
79. |
In the Commission's view, it may be difficult to reliably
estimate the net loss due to parking meters being taken out of
service for a particular construction project. Should this prove to
be the case, the Commission would consider it a suitable alternative
to recognize the causal impact through the 15% loading on plan
approval and inspection costs. |
| |
(iii) Pavement restoration |
|
80. |
There was general agreement that carriers should be responsible
for restoring the road surface to substantially its original
condition. The cost of pavement restoration is a causal cost that
municipalities should be able to recover from carriers placing
facilities in municipal rights-of-way, where the carrier does not
perform the work itself to the reasonable satisfaction of
the city. |
|
81. |
Vancouver stated that the type of repair depends on the existing
pavement material and the traffic loading of the street. It stated
that it has developed a schedule of rates (per square metre) for the
various types of repair, and that these rates are based on its
actual costs. |
|
82. |
In its example, Vancouver applied its schedule of rates, with the
addition of its proposed 62% loading, to calculate an applicable
charge of $124,554. |
|
83. |
The Commission considers it reasonable that Vancouver rely on a
standard rate schedule for pavement restoration, provided that the
schedule reflects the causal costs of restoration and is applied on
a routine and non-discriminatory basis to all parties performing
construction in the street. |
|
84. |
In addition, the Commission considers it appropriate that
carriers have the option of having their own contractors restore the
pavement, with the proviso that the work must meet any reasonable
standards set by the municipality as to time and quality of
work.
|
| |
(iv) Transit operating delays |
|
85. |
Vancouver proposed a charge intended to recover the cost of
delays to the public transit system resulting from construction
activities. In its example construction project, Vancouver
calculated the applicable one-time charge to
be $3,538. |
|
86. |
In the Commission's view, transit operating delay costs would be
disproportionately difficult or complex to determine accurately. The
Commission therefore considers that these costs should be recognized
as part of the 15% loading on plan approval and inspection
costs. |
| |
(v) Public delays |
|
87. |
Vancouver proposed that it recover costs of delays to the public
in cases of inordinately lengthy telecommunications
construction. |
|
88. |
As acknowledged by Vancouver, delays to the public do not entail
a cost to the municipality. Therefore, the Commission considers that
the municipality should not be permitted to recover any amount for
such delays. |
| |
c) Lost productivity for city operations |
|
89. |
Vancouver proposed to charge an annual amount intended to recover
the additional costs it incurs as a result of lost productivity in
city operations due to carriers' occupancy and use of municipal
rights-of-way (e.g., additional costs in street resurfacing, costs
of working around carriers' facilities in the
street). |
|
90. |
In its example construction project, Vancouver calculated the
applicable annual charge to be $478. |
|
91. |
The Commission notes that it has previously accepted loss of
productivity costs proposed by Bell Canada in the context of
determining rates for support structures. |
|
92. |
In the Commission's view, if significant additional costs are
incurred by Vancouver that are identifiable with the presence of
Ledcor's facilities, Vancouver should recover those additional costs
directly from Ledcor, with appropriate documentation and itemized
invoicing of costs. The Commission also considers that there may be
instances where it would be appropriate for Ledcor to perform any
required additional work itself. However, routine lost productivity
costs that cannot be directly linked to a specific carrier should be
recognized through the 15% loading on plan approval and inspection
costs. |
| |
d) Drainage of telecommunications company
vaults |
|
93. |
Vancouver noted that, as part of the installation of fibre optic
networks, carriers place access vaults along their networks. As
these vaults must be accessed from the street surface, removable
lids flush with the street level are placed on these structures.
These lids cannot be made watertight, and drainage from the vaults
to nearby sewer drainage pipes must therefore be
provided. |
|
94. |
Vancouver stated that the cost of installation of drainage
facilities provided by the city is currently recovered from the
company that requests the drainage. It proposed to continue to
recover this up-front cost based on its actual
costs. |
|
95. |
Vancouver also submitted that another cost component relates to
the runoff from the access vault. The regional government in
Vancouver is responsible for the collection of storm water drainage
and allocates its costs to member municipalities through a
volumetric charge. Vancouver stated that it currently charges the
companies an on-going fee related to this runoff based on the amount
charged by the regional government in Vancouver. It proposed to
continue to recover this on-going cost through annual drainage
fees. |
|
96. |
The Commission considers that, to the extent that the city pays
the regional government in Vancouver a volumetric charge for
draining water, the costs are causal and can be passed through
(i.e., with no loadings or mark-ups) to the relevant carrier.
Further, when the municipality incurs costs to connect the vaults to
the sewers, these costs can be passed on to the
carrier. |
| |
e) Pavement degradation |
|
97. |
Vancouver submitted that cuts in the pavement for utility
construction cause additional on-going repairs to pavement surfaces
(e.g., to fill cracks around utility cuts and to patch pavement). In
addition, the road requires more frequent full-width grind and
overlay repairs. Vancouver presented a study relating to
Ottawa-Carleton to support its claim for the recovery of the related
costs from carriers such as Ledcor. |
|
98. |
In Vancouver's example construction project, the charge would
amount to $859 annually (including the full 62%
loading). |
|
99. |
The Commission accepts that utility cuts contribute to the
degradation of pavement. Conceptually, the causal costs would be (a)
those associated with additional repairs (e.g., crack-filling), and
(b) the cost of the advancement of the grind and overlay
procedure. |
|
100. |
With regard to on-going repairs, the Commission considers that
Vancouver has provided insufficient justification for its allocation
of the associated costs among the various utilities. Further, costs
associated with grinds and overlays should be limited to the costs
of advancement, and be properly substantiated by a study related to
the municipality in question or to a municipality where conditions
are demonstrably similar. Finally, for the sake of ease of
application and administrative simplicity, the Commission considers
that these costs should be recovered through one-time charges, if
such charges can be developed. |
| |
f) Agreement and Utility Management Costs |
|
101. |
In discussing its example construction project, Vancouver noted
that it had stated in its initial application that there were
certain administrative costs that could not be related to specific
projects, such as time spent negotiating agreements. It had
therefore proposed that these costs be included through the use of a
multiplicative factor applied to direct and indirect costs.
Vancouver stated that it became apparent that these costs can be
readily identified and, in some cases, assigned to individual
companies causing them. Vancouver therefore proposed that a new
direct cost category be created called Agreement and Utility
Management Costs, broken down into up-front negotiating costs and
on-going utility management costs. |
|
102. |
Vancouver stated that negotiating costs would be based on staff
time spent in meeting with telecommunications companies and
reporting to City Council, and on clerical support for these
functions. Vancouver proposed to bill these costs to the carrier in
question based on a detailed accounting of staff time spent on each
agreement and the various hourly rates that Vancouver pays for that
staff time. |
|
103. |
Vancouver stated that a charge for negotiating costs would not
apply in its example construction project, since an agreement has
already been established. |
|
104. |
Vancouver stated that utility management costs relate to high
level decisions made reviewing and interpreting existing agreements,
developing policies related to the administration of agreements,
etc. It added that, in future, these costs would include
administration of joint municipal/utility committees to develop
better coordination mechanisms between various activities in the
streets, and the management of duct and trench sharing. Vancouver
calculated a base utility management cost of $0.035 per metre. In
its example construction project, the applicable charge would amount
to $39 per year. |
|
105. |
In its reply, Vancouver noted its intention to create, at the
completion of this proceeding, a new municipal access agreement that
it would wish to become, in the medium term, a standard for all
carriers. In the longer run, Vancouver stated that it intends to
create a by-law to which all users of street space could refer for
all relevant provisions for their use of street space. Vancouver
argued that, by recovering its costs of negotiation, it would
provide an incentive to carriers to decline to seek terms particular
to themselves. In addition, any costs that were incurred by
Vancouver as a result of such negotiations would be borne by the
carrier seeking exceptional treatment, rather than by the
taxpayer. |
|
106. |
In the Commission's view, negotiating and utility management are
common costs of operations. Some of these costs would be variable
common costs, and would therefore be recognized through a related
loading on direct costs (for example, Vancouver's proposed 62%
loading, minus the component for fixed common
costs). |
|
107. |
With regard to explicit negotiating costs, the Commission also
considers that permitting Vancouver to recover such costs would
remove an incentive for it to make reasonable concessions and to
bring negotiations to a timely conclusion. With regard to utility
management costs, the Commission notes Vancouver's intention to set
up a municipal/utility co-ordinating committee. As discussed above
(see Joint planning issues), the Commission encourages
such efforts and considers it appropriate that carriers contribute
to the costs of any such committee. The Commission considers that
there is merit to the suggestion that participants in such
committees should have flexibility to determine how best to share
these costs. |
|
108. |
Accordingly, the Commission does not consider it appropriate that
Vancouver explicitly recover costs associated with Agreement and
Utility Management. |
| |
g) Land charges |
|
109. |
Vancouver and other municipalities were of the view that they
should be entitled to recover "access" fees based on the "market
value" of the rights-of-way occupied and used by
carriers. |
|
110. |
Vancouver argued that a market-based mechanism is the best way to
ensure that this scarce resource is used efficiently and
effectively. Vancouver submitted that municipal property space
suitable for the placement of telecommunications facilities is
limited, and that not charging for space encourages excessive use of
it. Vancouver submitted that this puts subsurface space at a
premium, and results in excessive disruption of traffic as one
competitor after another cuts new trenches down the
street. |
|
111. |
Vancouver proposed to charge any competitive commercial user the
cost of the space occupied through an annual charge comparable to
what would be charged if the space were private property. Vancouver
added that charging others for the use of the space will provide an
incentive for it to not be wasteful in its own use, because to do so
would block use by others who would pay.
|
|
112. |
Vancouver proposed an annual per-metre charge to carriers for the
use and occupancy of rights-of-way based on the value of adjacent
lands. Vancouver's proposed formula is as
follows:
|
| |
Linear Rate = Land Value (based on land sales data for adjacent
lands) |
| |
x Rate of Return (Vancouver's borrowing
rate) |
| |
x Occupied Width (includes horizontal
clearances) |
| |
x Alienation Factor (adjustment to reflect the actual use,
i.e., the degree to which the land is "alienated" from other
uses). |
|
113. |
Vancouver stated that, if telecommunications companies co-located
their facilities in a trench, the fee would be calculated in the
same way, but would be shared by the various users of the trench.
This would support the objective of encouraging more efficient use
of public space, as there would be an incentive for
telecommunications companies to co-locate their
facilities. |
|
114. |
Municipalities and FCM argued generally that failure to charge
market-based rates would constitute a subsidy from taxpayers. They
added that such charges constitute an opportunity cost, in that
other users of right-of-way space are willing to pay such
fees. |
|
115. |
Carriers argued, among other things, that many of the concerns
identified by Vancouver would be addressed by proper joint planning
processes. While endorsing joint planning, FCM and municipalities
responded that it has its limitations, and is no substitute for
sending "proper price signals". |
|
116. |
The Commission notes that the land charges in the example
discussed in response to Vancouver(Bell/MTS)28Feb00-6 would amount
to $24,480 annually, for a 680 metre installation in the downtown
area, representing a per-metre annual charge of
$36. |
|
117. |
The Commission considers that, in most instances, it would be
extremely difficult to establish a "market-based" rate for the use
of municipal property, as there is no "free market", consisting of
totally willing buyers and sellers, for municipal consent to occupy
and use municipal rights-of-way. The Commission is not satisfied
that Vancouver's reference to adjacent lands is appropriate in these
circumstances, given that the land in which the right-of-way is
situate is a public street and in most instances will remain
dedicated to that purpose. By contrast, adjacent lands are largely
privately owned, are dedicated to diverse and essentially private
uses and are freely traded. In addition, the Commission notes that
much of the value of the adjacent land derives from the fact that
the land is serviced by "utilities" such as communications
carriers. |
|
118. |
Further, the Commission considers that, provided the
municipality's causal costs are recovered from carriers, as
discussed above with regard to other elements of Vancouver's costing
proposal, there is no issue of taxpayers "subsidizing" carriers, in
that additional costs imposed by the construction, maintenance and
operation of transmission lines would be absorbed by carriers, not
taxpayers. |
|
119. |
Finally, the Commission considers that many of the arguments and
concerns raised by Vancouver and other municipalities in support of
such fees (scarcity, congestion, etc.) can be addressed through
improved planning (see Joint planning issues,
above). |
|
120. |
In light of the above, the Commission concludes that the blanket
imposition of "market-based" charges is not necessary or
appropriate. |
|
121. |
The Commission considers that percentage of revenue fees raise
the same concerns as land-based charges. |
|
122. |
Accordingly, the Commission is not including a requirement for
Ledcor to pay a land-based charge in the terms and conditions of its
permission to Ledcor to construct, maintain and operate the
transmission lines in question. |
| |
Application to the 18 street crossings |
|
123. |
The record with regard to Ledcor's construction of transmission
lines in the street crossings at issue indicates that no pavement
was breached. Further, Ledcor stated in its initial reply of 27 May
1999 that it had applied to Vancouver to obtain consent to construct
its transmission lines under one city street that crossed the
railway right-of-way where it was placing its facilities, and that
the other 17 "street crossings" are actually municipal road
allowances across that right-of-way. Accordingly, based on the
record, the Commission considers that many of the cost elements
proposed by Vancouver do not apply to the specific Ledcor
case. |
|
124. |
Applying the approach set out above to the facts of the
particular case, the Commission concludes that Ledcor should pay
Vancouver for the plan approval and inspection charges that would
result from the application of Vancouver's proposal, with the
adjustments discussed earlier, to the 18 street crossings in
question. The resulting charges are a flat fee of $1,127, plus a
per-metre charge of $8.67, for a total of $7,613. |
|
125. |
Given the Commission's conclusion that no pavement was breached,
or to the extent that Ledcor has satisfactorily carried out any
repairs itself, no charges for pavement restoration should
apply. |
|
126. |
Based on the record, it appears that traffic signing was not
necessary for Ledcor's construction in the 18 street crossings.
Accordingly, no charges for traffic signing should
apply. |
|
127. |
Similarly, based on the record, it appears that no drainage
facilities were provided by Vancouver. Therefore, no charges for
such connections would apply. |
|
128. |
In its comments, Vancouver requested that the Commission order
Ledcor to pay interest, from the date of the Commission's interim
order in this proceeding, on any amount that the Commission might
order Ledcor to pay to the city. The Commission does not consider
that interest is warranted in the circumstances of this case.
Accordingly, the Commission denies Vancouver's
request. |
|
129. |
As discussed above, the plan approval and inspection charges that
Ledcor will pay to Vancouver pursuant to this decision recognize any
routine losses of productivity that Vancouver may experience due to
the presence of Ledcor's transmission lines in the 18 street
crossings. If in future Vancouver incurs significant additional
costs that are identifiable with the presence of Ledcor's
transmission lines, it may recover those additional costs directly
from Ledcor, upon presentation of the appropriate documentation
including an itemized invoice of costs. Alternatively, it may be
appropriate for Ledcor to perform any required additional work
itself. |
| |
Relocation costs |
|
130. |
Vancouver submitted that it should not be responsible for the
cost of relocating telecommunications facilities if relocation is
required for municipal purposes. Vancouver added as a caveat on the
application of this principle that the municipal government must act
reasonably in co-ordinating the many uses of the public property in
a manner that does not cause unnecessary or premature disruptions to
telecommunications plant. |
|
131. |
Vancouver proposed that relocation costs be incurred directly by
the carrier if it undertakes the work, or be invoiced to the carrier
if the city undertakes the work. It stated that these costs are
project-specific and should be invoiced on a project-by-project
basis. |
|
132. |
Vancouver stated that much of the work that takes place on city
streets is related to redevelopment of private property for which
the city cannot fully plan or give advance notification. Vancouver
also stated that redevelopment of private property, for example, for
a shopping development, sometimes requires reconfiguring the
adjacent street to accommodate changed traffic patterns. It noted
that, in this case, it requires the developer to pay for the street
changes and that it would be appropriate for the private developer
to pay for costs of relocating the carrier's
facilities. |
|
133. |
FCM and municipalities supported Vancouver's position on
relocation costs. FCM stated that, where relocation or adjustment is
required for bona fide municipal purposes, the utility should
be 100% responsible for the costs. In response to interrogatory
FCM(CRTC)28Feb00-5, FCM stated that a bona fide municipal
purpose is any purpose that is authorized at common law or by
statute, for example, bridge reconstructions, improvements such as
road widenings and municipal landscaping, infrastructure
replacements, transit lane relocations, and the burial of aerial
lines for safety, municipal redevelopment, security or other
reasons. |
|
134. |
Carriers objected to Vancouver's proposal, arguing, among other
things, that: (a) Vancouver's approach would eliminate an incentive
to municipalities to behave reasonably and consult properly with
respect to relocation matters; and (b) a satisfactory approach
to the allocation of relocation costs should be sensitive to the
facts of a particular situation. |
|
135. |
Bell Canada/MTS submitted that they have not traditionally been
required by municipalities, as of right, to assume costs to relocate
their plant located in public rights-of-way when a municipality
requires it, but have generally negotiated the assumption of such
costs on a case-by-case basis, or if applicable, adopted mechanisms
set out in provincial legislation or regulations. They added that
their experience with case-by-case negotiations is that the process
is administratively burdensome, for themselves as well as for the
municipality. They considered that the existing process could be
streamlined to the benefit of both themselves and the
municipalities. Therefore, in their model municipal consent
agreement filed in this proceeding, Bell Canada/MTS proposed an
alternative mechanism which, they stated, Canadian carriers and
municipalities could choose to adopt. They described that mechanism
as follows: |
| |
|
| |
As municipalities have in place planning "windows" which
typically span five or more years for projects of a scale which
would require the relocation of underground utilities, relocations
in the first five to ten years after construction of Canadian
carrier plant are unusual. After this period, the allocation of
relocation costs has typically been subject to negotiations. The
mechanism put forward by the Companies in the model agreement
codifies, on a going forward basis, such arrangements. Within an
initial period which is well within municipal planning time frames,
costs associated with relocation at the initiative of the
municipality are allocated to the municipality. Following this
period, a sliding scale is applied for a period of five years.
Following the 9th year, the Canadian carrier would
henceforward assume all the costs associated with the relocation of
its plant. Since equipment is typically operated in rights-of-way
for a period of decades once installed, the result is that for most
of the useful life of its equipment, the Canadian carrier will be
responsible for all costs associated with the relocation of its
equipment in municipality initiated relocations. The Companies
believe that the mechanism they have codified in the model agreement
is fair to all parties, provides certainty as to the specific terms
thereby simplifying administration and provides an incentive to
municipalities to conduct advance planning. The Companies reiterate
that such advance planning by municipalities is routinely conducted
today. |
|
136. |
The Commission considers that sections 42 to 44 of the Act give
it the jurisdiction to impose conditions relating to relocation
matters, whether at the time of construction or afterwards. The
Commission also notes that its predecessor bodies have generally
declined to impose terms and conditions relating to relocation at
the time of construction, preferring instead to consider the matter
at the time the requirement for relocation arises, having regard to
the circumstances then applicable. |
|
137. |
Consistent with the above, the Commission is not prescribing a
mechanism governing the allocation of the cost of any future
relocation of Ledcor's transmission lines. If Vancouver requires the
relocation of these lines at some time in the future, the Commission
considers that the parties should negotiate the allocation of costs,
taking into account the factors noted below, or adopt some
administratively simple mechanism such as that advanced by Bell
Canada/MTS. Failing an agreement, either Vancouver or Ledcor could
apply to the Commission to resolve the dispute. |
|
138. |
The Commission would generally consider it appropriate to take
into account the following factors in allocating costs between the
municipality and the carrier: (a) who has requested the relocation,
i.e., the municipality, the carrier, or a third party; (b) the
reason for the requested relocation (e.g., safety reasons, aesthetic
reasons, to better serve customers); and (c) when the request is
made vis-à-vis the original date of construction (e.g., whether the
request is made a considerable length of time after the original
construction, or very shortly after that time). |
| |
Fixed term of agreement, termination provisions, termination on
default |
|
139. |
The SCA attached to Ledcor's original application provided that
the rights granted to Ledcor under the agreement would expire in 20
years, unless cancelled prior to expiry pursuant to provisions
related to default (Article 2.3). The agreement also provided for
perpetual renewal for successive 10-year periods. However, Vancouver
could decline to renew the agreement on written notice to
Ledcor. |
|
140. |
The MAA provided by Ledcor also specified a 20-year
term. |
|
141. |
Under the SCA (Article 12), neither party could make use of the
fibre in question where: (a) the city cancelled the agreement for
default; (b) the agreement had expired and the company breached a
surviving obligation; or (c) no new agreement had been reached
within one year of the expiry of the old agreement. In addition, the
city could require removal of the fibre. If the company did not
remove it within one year, the fibre would be deemed abandoned and
title would vest in the city. The MAA contained similar provisions
(Article 12), with certain changes specific to Ledcor's grant of
dark fibre to the city. |
|
142. |
In its application, Ledcor stated that it requires secure access
for a minimum of 40 years (a 20-year term plus two automatic
renewals of 10 years), consistent with the useful life of the
telecommunications system being installed. |
|
143. |
Carriers objected to provisions that would limit the term of the
municipality's consent. Generally, they argued that municipal
consent, once granted, cannot be withdrawn. Further, if an agreement
were to have a fixed term, it should be very clear that the expiry
of the agreement would not affect a distribution undertaking's right
of access . |
|
144. |
As discussed earlier, the Commission considers that carriers do
not have an unqualified right to enter on and break up any highway
or other public place for the purpose of constructing, maintaining
or operating their transmission lines. Similarly, the Commission
does not consider that they have an unqualified right to "remain
there for as long as necessary" for that purpose. The carrier's
rights are subject to both an obligation not to unduly interfere
with public use and enjoyment and to a requirement for municipal
consent (or the Commission's permission). |
|
145. |
In the Commission's view, changes in circumstances may require
that agreements entered into by municipalities and carriers be
renegotiated periodically. Accordingly, it is reasonable for
municipalities to take the position that any consent for carriers to
occupy and use municipal rights-of-way should be limited to a fixed
term. |
|
146. |
In the Commission's view, the more important consideration is the
consequence of the expiry of an agreement, of a termination notice
or of a cancellation for default. The Commission agrees with parties
who argued that municipalities must not interfere with the operation
of the carrier's network (e.g., require the carrier to cease
operations or remove its facilities) when an agreement has expired
or been terminated or cancelled, and parties are unable to agree on
new terms and conditions. The Commission notes that such
interference could result, among other things, in an unnecessary
interruption of service to the carrier's customers. The Commission
further agrees with those parties who argued that the appropriate
recourse under such circumstances is for one party or the other to
seek the Commission's assistance.
|
|
147. |
In the case of the 18 street crossings, it is this decision,
rather than an agreement between the parties, that sets out the
terms and conditions under which Ledcor may construct, maintain and
operate its transmission lines. Should changed circumstances require
a change to the terms and conditions of that permission, one or both
of the parties may apply to the Commission.
|
| |
Liability, indemnity, insurance |
|
148. |
In its initial application of 19 March 1999, Ledcor stated that
Vancouver's proposed SCA and MAA provided that Ledcor would be
obliged to indemnify Vancouver against all forms of injury, loss and
damage (including economic losses) arising from Ledcor's activities
under the agreement, while Vancouver would be absolved from
liability for all forms of injury, loss and damage (including
economic losses) arising out of Vancouver's activities, even where
the injury or loss occurred as a result of "the negligence or
willful acts or omissions of the city or its employees." Ledcor
submitted that such provisions are one-sided and unfair, and are not
acceptable to Ledcor.
|
|
149. |
Vancouver argued that protection from liability for city
interference with telecommunications facilities is clearly in the
public interest. FCM and the municipalities expressed similar
views. |
|
150. |
The Commission rejects arguments by FCM (and others) as to
limitations on the Commission's jurisdiction under sections 42 to 44
of the Act to prescribe terms and conditions relating to limitations
of liability. As noted earlier, where a carrier cannot obtain
consent from a municipality on acceptable terms, the Commission may
grant the permission "subject to any conditions that the Commission
determines" (section 43(4) of the Act). The only qualification in
the subsection with respect to the scope of the Commission's
jurisdiction is that the Commission must have due regard to the use
and enjoyment of the highway or other public place by
others.
|
|
151. |
The Commission notes that, under section 43, carriers have a
qualified right to enter on and break up any highway or other public
place for the purpose of constructing, maintaining or operating
their transmission lines, subject to a duty not to unduly interfere
with the public use and enjoyment of the highway or other public
place. The Commission agrees with TELUS that one-sided liability
provisions such as those proposed by Vancouver are not necessary in
order to ensure that carriers fulfill this duty. The Commission also
considers that there is merit to the arguments of TELUS, CCTA and
others that the ordinary provincial principles of liability for
negligence should apply to encourage all users of rights-of-way,
including municipalities, to take care and ensure that their
activities do not harm others. |
|
152. |
The Commission notes Vancouver's argument that damage to
carriers' facilities is often occasioned by inadequate protection,
such as wooden ducts placed by BC TEL that are rotting away but are
still in use in many locations in city street space. The Commission
considers that such concerns should also be addressed pursuant to
the ordinarily applicable provincial principles of
liability. |
|
153. |
The Commission considers conditions 27 and 28 of the Bell
Canada/MTS model municipal consent agreement to be appropriately
balanced. The Commission also notes that several participants in
this proceeding argued that parties may wish to exclude
consequential or economic losses, which is the effect of Bell
Canada/MTS' proposed condition 29. The agreement between Group
Telecom and Calgary, advanced as a model by Group Telecom, contains
generally mutual liability provisions and excludes damages for
consequential losses, but also adds the following: |
| |
|
| |
The City shall not be liable to, nor indemnify and save harmless,
Group Telecom, pursuant to subsection (2) where: |
| |
(a) the City has not been advised in writing of Group Telecom's
Installations being placed in a Highway and Group Telecom has,
following a request by the City or any other Party, failed to
identify the location of its Installations; or |
| |
(b) the City has corrected a default of Group Telecom's pursuant
to the provisions of this Agreement provided the City is not
negligent in its corrective action. |
|
154. |
The Commission sees no reason to object to the inclusion of such
provisions. |
|
155. |
In light of the above, the Commission is not prescribing terms
and conditions related to liability in this decision. The Commission
would have no objection if Vancouver and Ledcor were to agree to
provisions similar to those in Bell Canada/MTS's model municipal
consent agreement or in Group Telecom's agreement with Calgary.
Absent such agreement, provincial principles of liability for
negligence would apply. |
|
156. |
In light of the above, the Commission would consider it
reasonable for each party to seek assurance from the other that it
is adequately insured or can self-insure, in light of its potential
liability . |
| |
General security agreements, letters of credit |
|
157. |
The SCA advanced by Vancouver during its negotiations with Ledcor
would have required Ledcor to execute a General Security Agreement
(GSA) with respect to its network in favour of the
city.
|
|
158. |
In addition, it contains a requirement that, in order to obtain
the city's permission for "new work" (e.g., construction), Ledcor
must submit a letter of credit, valid for at least one year, equal
to 100% of the estimated cost of the relevant restoration work, as
determined by City Engineer (applying generally applicable formulas
and principles). |
|
159. |
The SCA further specifies that the letter of credit be renewed
and replaced as required during the time the work is on-going. After
the new work is satisfactorily completed, the letter of credit would
be replaced with a new letter of credit equal to 20% of the value of
the initial work. This subsequent letter of credit would be valid
for at least one year.
|
|
160. |
Ledcor argued the following with respect to these
requirements: |
| |
|
| |
The Applicant considers these security obligations to be unduly
burdensome, costly and restrictive requirements for municipal
consent to cross a few streets on an existing railway right-of-way.
Proper cost-based municipal access fees for access to such street
crossings should be nominal, and security obligations minimal or
non-existent. In fact, the applicant would consider prepaying the
whole of a reasonable cost-based access charge in
advance. |
|
161. |
The Commission considers a requirement to enter into a GSA to be
unduly onerous, and unnecessary to ensure that Ledcor will meet its
obligations under the terms and conditions of the Commission's
order. |
|
162. |
With regard to letters of credit, the Commission considers it
reasonable that municipalities would request some assurance that
construction work (e.g., pavement restoration) will be completed
satisfactorily. In the Commission's view, that assurance could be
provided by various means, including a letter of credit or, for
example, the deposit of a reasonable sum of money to ensure the
satisfactory doing of the work. |
| |
Applicable law |
|
163. |
In its original application, Ledcor stated as
follows: |
| |
|
| |
Various provisions of Article 13 of the proposed [street
crossing] agreement would impose provincial legal jurisdiction over
matters that are properly subject to federal telecommunications law.
In particular, disputes over access to municipal property by a
Canadian carrier are subject to CRTC jurisdiction under sections 43
and 44 of the federal Telecommunications Act.
|
| |
Notwithstanding the CRTC's clear jurisdiction over municipal
access disputes with Canadian carriers, Article 13.7 purports to
make the entire SCA subject "in all respects" to the laws of British
Columbia. Article 13.8 provides that disputes under the agreement
will be settled by the courts of British Columbia rather than the
CRTC. Article 13.6 establishes a detailed dispute resolution
procedure that is one-sided (in the City's favour) and purports
to require access disputes to be resolved by audit and arbitration
proceedings rather than by the CRTC under the Telecommunications
Act. |
|
164. |
The Commission considers it inappropriate to include in
agreements provisions stating that disputes will be settled only by
the courts of a particular province and only according to the laws
of a particular province. In the Commission's view, relevant
provisions should state that the agreement will be governed by, and
construed in accordance with, the laws of the province in which the
municipality is situate and the laws of Canada applicable
thereto.
|
| |
Third party issues |
|
165. |
As described earlier, the MAA advanced by Vancouver in its
negotiations with Ledcor contained provisions requiring Ledcor to
pay an annual licence fee, based on Ledcor's gross revenues from
telecommunications services provided to customers whose equipment or
other apparatus was connected to Ledcor's network in Vancouver and
reasonably allocable to that network (the Vancouver portion of gross
revenues). |
|
166. |
In support of these provisions, the MAA required that Ledcor
provide information, by affidavit, regarding the Vancouver portion
of gross revenues, including audited financial statements,
particulars as to the calculation of the gross revenues, and a
schedule of published rates charged to customers. |
|
167. |
Under the MAA, Ledcor would also be obliged to permit Vancouver's
auditors to inspect all Ledcor's financial record, profiles,
contracts, etc., relating in any way to any matter governed by the
agreement. |
|
168. |
The SCA contained provisions which would require Ledcor to
provide extensive details as to parties to whom it granted a
"sub-licence" of its rights and obligations under the agreement
(i.e., a "sub-licence" to acquire IRUs with respect of the fibre, or
to own, operate or use any part of the fibre). Any such sub-licence
would have to provide that the sub-licensee would be bound by
Ledcor's obligations under the agreement, to the same extent as
Ledcor. Ledcor would be required to provide annual reports, by
affidavit, as to the current status of all
sub-licences. |
|
169. |
In its initial application, Ledcor stated that its fibre optic
system in Vancouver consists of fibre optic cable installed in (a)
conduits constructed by Ledcor in a CPR right-of-way that intersects
city streets, and (b) TELUS ducts along a route between the CPR
right-of-way and the Oak Street Bridge in south Vancouver (pursuant
to the support structure tariff). |
|
170. |
The MAA advanced by Vancouver would require the city's prior
written licence for the installation of Ledcor lines and facilities
in the existing conduit of third parties. Further, it would appear
to require the extension of the terms of the MAA, including
percentage of revenue fees, to lines and facilities that Ledcor had
already installed in conduit owned by BC Hydro and Power Authority
or by British Columbia Telephone Company prior to February 1999.
|
|
171. |
Ledcor objected to these provisions. |
|
172. |
In its submission of 28 January 2000, Vancouver stated that it
would not require information about purchasers, lessees or other
third parties using fibre or duct space owned by the carrier, unless
such parties would be undertaking work on city streets outside of
the duct structures of the carrier with whom the city has an
agreement. Vancouver stated that, whenever a third party wishes to
undertake work on the streets, it would require a further agreement
with that third party. |
|
173. |
Under the terms and conditions established by the Commission in
this decision, Ledcor is not obliged to pay percentage of revenue
fees. Accordingly, there is no need for Ledcor to provide Vancouver
with information related to the calculation of such fees, or for
related audit requirements. |
|
174. |
The Commission considers that parties merely occupying Ledcor's
support structures or (like some of the respondents to Vancouver's
initial application) merely acquiring strands on Ledcor's fibre
optic system should not be obliged to pay separate fees to
Vancouver. Further, such parties should not be obliged to seek
Vancouver's consent, unless they are undertaking excavation in the
streets or some other activity that would cause disruption, for
example, to traffic. Accordingly, there is no reason to require
Ledcor to provide information to Vancouver with respect to such
parties. |
|
175. |
Similarly, the Commission finds that Ledcor should not be obliged
to pay separate fees to Vancouver merely by virtue of the presence
of its transmission lines in the support structures of other
parties, such as TELUS. |
|
176. |
Bell Canada/MTS's model municipal consent agreement (Article 30)
contained the following provision: |
| |
|
| |
a) the Company's Support Structure License Agreement requires the
third party to comply, at the third parties' sole expense, with
all laws, statutes, by-laws, codes, ordinances, rules, orders and
regulations of all governmental authorities in force, and that the
third party shall obtain and maintain any and all permits, licenses,
official inspections or any other approvals and consents necessary
or required for the placement or operation of the third party's
equipment structures …. |
|
177. |
The Commission considers that, should Ledcor make its support
structures available to others, it is sufficient that its agreements
with those third parties include a provision similar to that cited
above, modified (a) to reflect the fact that Ledcor does not have a
support structure tariff, and (b) by the insertion of the word
"applicable" before the phrase "laws, statutes, by-laws, codes,
ordinances …". |
|
178. |
As noted above, the MAA and SCA also contained extensive limits
on Ledcor's ability to assign the agreement, in whole or in part.
The Commission sees no reason for the inclusion of limitations as
extensive as those in the MAA and SCA. Rather, the Commission
considers that assignment provisions more consistent with other
agreements would be appropriate. For example, the Commission
considers that conditions 36 to 38 of the Bell Canada/MTS model
municipal consent agreement would be sufficient to protect the
interests of the municipality, without unduly constraining the
activities of the carrier. |
| |
Existing agreements |
|
179. |
In PN 99-25,
the Commission requested comment on whether any terms and conditions
imposed by the Commission in relation to the agreements for access
in Vancouver that are in dispute could and should replace the terms
and conditions in existing agreements that are not in dispute,
relating to municipal access in Vancouver.
|
|
180. |
As indicated earlier, the Commission considers that, in enacting
sections 43 and 44 of the Act, Parliament has provided a mechanism
whereby disputes can be resolved when carriers and municipalities
cannot agree on the terms and conditions under which carriers will
be granted consent to construct transmission lines. Consistent with
this view, the Commission considers it inappropriate to replace the
terms and conditions of agreements that are not in dispute before it
by virtue of an application brought pursuant to section 43 or
44.
|
| |
Disposition |
|
181. |
The Commission, by majority, grants Ledcor, and any of its
affiliates currently operating as Canadian carriers in Vancouver,
permission to construct, maintain and operate the transmission lines
at issue in this proceeding in the 18 street crossings in
question. |
|
182. |
Ledcor is directed to pay forthwith to Vancouver the sum of
$7,613. |
|
183. |
Ledcor is directed to provide to Vancouver, as soon as
practicable, "as-built" drawings sufficient to accurately establish
within the street crossings the exact location, elevation and
distance of the transmission lines, in both paper and electronic
form. |
|
184. |
Vancouver and Ledcor are directed to exchange forthwith lists of
emergency contacts.
|
| |
Secretary General
|
| |
This document is available in alternative format upon request
and may also be examined at the following Internet site: http://www.crtc.gc.ca/
|