PTFP Close-Out and Federal Interest Period Requirements
for Construction Grants (September 2001)


We have estimated that each response to this collection of information will take on average 24 hours for construction grant recipients to prepare the certification of completion, final inventory, and final lien. Our estimate includes the time to read the instructions, look through existing records, gather the required data, and complete and review the response. If you have any comments on this estimate or how we can improve the collection and reduce the burden it causes you, please write to the Office of Policy Coordination and Management, NTIA, Room 4892, Department of Commerce, Washington, DC 20230. Your comments will also be accepted via the Internet if you send them to. You are not required to respond to a collection of information sponsored by the Federal government, and the government may not conduct or sponsor this collection, unless it displays a currently valid OMB control number or if we fail to provide you with this notice.
OMB Approval No. 0660-0001. Expires July 31, 2006.



Introduction

The information presented here is meant to assist you in closing out your Public Telecommunications Facilities Program (PTFP) construction or planning grant. We urge you to read it carefully and to refer to the appropriate sections again as you prepare each item for your close-out. We encourage you to call your Program Officer at (202) 482-5802 if you have any questions.

The documents you need to submit in order to close out your grant are described in the sections that follow. Also included is a checklist on which you can record relevant information about your close-out. All of the items on the checklist are important to the close-out process. We suggest you print out one for your grant as soon as possible and refer to it as you prepare your close-out.

Please remember that all close-out documentation -
  • is due within 90 days of the completion of the grant project or the expiration of the Grant Award Period, whichever comes first; and


  • must include an original and one copy of all documents, with the full grant number (e.g., 99-01-99999) on each document.

Failure to provide the required information on time and in full not only creates unnecessary problems for you and needless work for the PTFP staff, but also puts your project out of compliance with the terms and conditions of your grant award. Being out of compliance can result in -

  • termination of the award,


  • establishment of an Account Receivable for all Federal funds paid to your organization, and


  • denial of future grants to your organization.




Documents Required to Close-Out Construction Grants

  • Certification that the project has been completed satisfactorily and insurance coverage obtained.
  • Final inventory of all equipment acquired as part of the grant project.
  • A priority lien on all equipment in the project.
  • Any other documentation relevant to the project, as required.

PLEASE NOTE CAREFULLY:

  • Under OMB rules, close-out documents and financial reports cannot be accepted even one day after the end of the 90-day close-out period. If you are late, you must seek a retroactive extension of the close-out period. Your request must be supported with justification in the form of an explanation of why you were unable to file your close-out on time.


  • In addition, failure to submit your close-out package within the 90-day period can result in the establishment of an account receivable for all Federal funds paid to your organization.


  • All documents except the lien form should be submitted in DUPLICATE with ORIGINAL SIGNATURES where required (please also include a photocopy of each lien form).


  • A copy of the approved final inventory must be stapled to each lien document when it is filed.
Please submit closeout documents in duplicate!


Contents

Closing Out Construction Grants

  Certification
  Final Inventory
   
  • Taxes, Shipping, Installation, & Other Project Costs
  •    
  • Preparing the Final Inventory
  •    
  • Total Project Cost
  •   Labeling Equipment
      Insurance Coverage
      Audit Requirements
      Priority Lien Requirements
       
  • Uniform Commercial Code (UCC) Forms
  •    
  • Completing the UCC Form
  •   FCC Documents
      Site Rights
      Construction Grant Close-Out Checklist

    Review of Close-Out Documents


    The Federal Interest Period

      Retention of Records
      Inspections
      Annual Status Reports for Construction Grants
      Continuation of the Lien
      Checklist for Federal Interest Period


    Where to Send Close-Out Documents

    Your PTFP Program Officer should be the initial contact for all programmatic aspects of closing out your grant award. The reports and other documents you submit to NTIA/PTFP at close-out are:
                Certification of Completion  
               Final Inventory  
               Insurance Certification  
               Lien  
               Site Rights Certification (if required and not already submitted)  
               FCC Documents (if required and not already submitted)  
    They should be addressed to:
    	
    		[Program Officer's Name]
    		NTIA/PTFP
    		Room 4812
    		U.S. Department of Commerce
    		1401 Constitution Avenue, NW
    		Washington, DC  20230
    	
    The name of your organization's PTFP Program Officer is listed in the Special Award Conditions of your grant award document.

    The National Institute of Standards and Technology (NIST), Grants & Agreements Management Division (GAMD), is the Commerce Department's Federal Grants Office and is responsible for all administrative and financial aspects of closing out your grant award. The reports you submit to GAMD at close-out are:

               Financial Status Report (SF-269)  
               Request for Advance or Reimbursement (SF-270)  
               Cash Transaction Report (SF-272)  
               Executed liens (those that have been filed and
             stamped in a recording office in your state)
     

    They should be addressed to:
    
    		[Grant Specialist's Name]
    		National Institute of Standards and Technology
    		Office of the Chief Financial Officer
    		Grants & Agreements Management Division
    		100 Bureau Drive, Mail Stop 3580
    		Gaithersburg, MD  20899-3580
    
    	

    The name of your organization's GAMD Grants Specialist is listed in the Special Award Conditions of your grant award document.

    Closing Out Construction Grants

    As noted above, all construction grant close-outs include at least three separate documents — a certification of completion and insurance coverage, a final inventory, and a priority lien. Here we discuss each of the three documents in turn.

    Hand Image Noting Important Text If additional documentation is required, PTFP will let you know.

    Certification


    The First item that must be included in your close-out documentation is certification that the project has been completed and that all of the terms and conditions of the award have been complied with.

    The certification should be in the form of a letter addressed to William Cooperman, Director, Public Broadcasting Division, and must refer to your full grant number (e.g., 99-01-99999). The letter should be signed by the same person who signed the Financial Assistance Award (Form CD-450) to accept the grant or by that person's successor or superior. The letter should certify specifically that your organization has:

    Mark for List Item complied with all of the terms and conditions of the grant;
    Mark for List Item acquired all of the facilities specified in the grant and that they have been installed, are in operating order, and being used to provide public telecommunications services in accordance with the project as approved by NTIA;
    Mark for List Item obtained all FCC authorizations necessary to operate the project apparatus;
    Mark for List Item obtained and will maintain adequate insurance to protect the Federal interest in the event of loss through casualty;
    Mark for List Item acquired all necessary site rights required for the project; and
    Mark for List Item attached a complete and accurate final inventory of equipment and final accounting of all project expenditures.


    Hand Image Marking Important Section Please submit two copies of the certification.

    Final Inventory

     

    You must supply two copies of a final inventory of all equipment (whether bought or donated) acquired as part of your PTFP-funded grant project. The inventory you submit will be compared with the equipment list approved as part of the Grant Award, along with any amendments approved in writing by the National Institute of Standards and Technology, Grants & Agreements Management Division (GAMD) during the project period.

    The inventory must include the following information for each item of equipment (an example of the format to use appears below):

    Mark for Listed Item a brief description of the item (e.g., "color camera", "CD player", "audio production console", "master control switcher");
    Mark for List Item the make and manufacturer's model number;
    Mark for List Item manufacturer's serial number;
    Mark for List Item the inventory number that your organization has assigned to the item (this number and the NTIA/PTFP grant number must both be on a label attached to the item);
    Mark for List Item the quantity purchased of each item;
    Mark for List Item the per-unit cost of the item, if applicable; and
    Mark for List Item the total price of the item.

    Taxes, Shipping, Installation, and Other Project Costs

    Sales taxes and reasonable shipping charges may be claimed for equipment approved for a PTFP project. (Some states may waive sales taxes if the item is paid for with Federal funds.) Labor costs for project equipment installation can be claimed only when authorization was included in the award document or in an amendment approved in writing by GAMD.

    Sales Tax
    • Sales tax charges are usually included in the cost of an item.

    • When many items are purchased on a single invoice or purchase order, the sales taxes may be shown as a separate entry to cover that group of equipment items.

    • Sales tax charged may be grouped and listed as a single item at the end of the equipment list, when appropriate.
    Shipping
    • Shipping charges are usually included in the cost of an item.

    • When many items are purchased on a single invoice or purchase order, the shipping charge may be shown as a separate entry to cover a group of equipment items.

    • Shipping charges may be grouped and listed as a single item at the end of the equipment list, when appropriate.
    Installation
    • A number of small hardware items that do not relate to any one single item may be grouped in the inventory under a heading such as "Miscellaneous installation hardware" as long as it is made clear what sort of items make up the "miscellaneous" grouping.
    • We repeat: installation labor costs can be claimed ONLY WHEN AUTHORIZATION WAS INCLUDED IN THE FINANCIAL ASSISTANCE AWARD DOCUMENT OR IN AN AMENDMENT APPROVED IN WRITING BY GAMD.
    • Installation labor costs - when allowed - should be organized by payee and reported in the same detail as equipment.
    Other Project Costs
    • Other project costs can be claimed only when authorization was included in the Financial Assistance Award document or in an amendment approved in writing by GAMD.
    • Other project costs - if authorized - should be arranged by payee and reported in the same detail as equipment items.

    Preparing the Final Inventory

    Please provide a heading that includes the name of your organization and the complete NTIA/PTFP grant number (e.g., 99-01-99999). Please repeat the heading on each page of the inventory and number the pages.

    The Final Inventory list itself should be divided in half vertically, as shown in the example below. The left hand side should reproduce the equipment list from the award document; the right-hand side should show what was actually acquired.

    Each major item of equipment should be listed separately. In deciding what to include as major inventory line items, you should strike a balance between encompassing too much in a single entry (e.g., "six microwave hops...$360,000") and breaking entries down into unmanageable detail (e.g., "twelve wing nuts...$1.19).

    Minor equipment items, however, may be included in the cost of the major item to which they relate. You should note what sub-items are included in the total item cost. Any item that requires its own inventory number should be listed separately on the Final Inventory.

    You should include brief explanations of any aspect of the Final Inventory that is unusual and might, therefore, be questioned.


    Total Project Cost

    The total amount of the Final Inventory (including sales taxes, shipping, installation charges, and any other approved project costs) should equal the total reported on the final financial report (SF-269) submitted to the National Institute of Standard and Technology, Grants & Agreements Management Division.

    Note: Equipment lists will not be amended retroactively as part of closing out a grant in order to cover items purchased without prior written authorization from the National Institute of Standards and Technology, Grants & Management Division.

    Hand Graphic Marking Item to Note Please submit TWO copies of the final inventory
    (in addition to the copies attached to the final lien).



    SAMPLE FINAL INVENTORY

    Anytown State University

    Station WPS

    Anytown, State

    NTIA/PTFP Grant No. 58-01-33333

    Approved Equipment List Purchased Equipment List
    Description Manufacturer, Model Qty Cost Manufacturer, Model Serial No. Inventory No. Qty Unit Cost Price
    CATEGORY A - DISSEMINATION EQUIPMENT
    FM transmitter Connors 25 kw xmtr w/spare 1 $71,519 Warriner xmtr AT 25kw AT25-20045 99999-203 1 $69,778 $69,778
    FM antenna Mellone 4-bay antenna 1 14,000 Mellone 4-bay antenna 67893 99999-202 1 15,432 15,432
    Transmission line Harland heliax and hangers 500' 12,000 Chadwick heliax and hangers n/a n/a 365' 22 8,030
    Installation 8,000 Cooperman Techworks Co. n/a n/a 1 lot 8,342 8,342
    CATEGORY B - ORIGINATION EQUIPMENT
    Reel-to-reel ATR Sheppard Studio 524 2 11,780 DELETED, PER AMENDMENT 11/30/9?
    RDAT ATR Dyer RDAT 342X (PER AMENDMENT 11/30/XX 2

    8,490 Sanders RD-1230 SRD-0897 99999-200
    99999-201
    2 4,245 8,490
    Audio console Stewart ND-101 w/mon amp 1 20,000 Hallock STU-322 STU-68943 99999-204 1 19,836 19,836
    Cabinet Custom-built for console 1 3,000 Rivera Woodworks, Inc. n/a 99999-205 1 2,413 2,413
    APPROVED TOTAL PROJECT COST $148,789 ACTUAL TOTAL PROJECT COST $132,321


    Labeling Equipment

     

    You must mark permanently all equipment included in the project to ensure accurate identification and accurate reference to inventory records. Even if your organization does not normally assign inventory numbers to items costing under a specific dollar amount, you must still assign inventory numbers to all equipment items for NTIA's purposes.

    A non-removable label (or other means of identification) should be attached to the equipment where it can be seen easily. The label should contain your organization's inventory number plus the NTIA/PTFP grant award number.

    Transmission antennas should be assigned an inventory number. The number should be posted in the transmitter shelter with an appropriate identification.

    Insurance Coverage

     

    The requirement to submit a certificate from your insurance carrier or your risk manager has been dropped from the close-out requirements. This does not mean that you no longer have to insure equipment acquired as part of a PTFP grant.

    You still must have insurance so that, in the event of loss, you will be able to continue the project by replacing equipment promptly. The insurance must protect the equipment from common hazards (fire, theft, etc.). Flood insurance should be carried in a community where such insurance is available when the grant equipment is to be located in an area that has been identified by the Secretary of Health and Human Services as having special flood hazards.

    Although you no longer have to provide a certificate from your insurance company or risk manager, you must certify that your organization has - and will maintain - the required coverage. This certification is part of the letter of certification.


    Audit Requirements

     

    If your organization expends more than $300,000 in Federal funds - from all Federal sources, not just PTFP - in a one-year period, you must have an audit performed in accordance with Federal guidelines as stated in OMB Circular A-133, dated June 30, 1997 (copies were included in the grant award package).

    These audits are performed in one of two ways. An NTIA/PTFP-specific audit may be performed if your organization receives Federal funds only from NTIA. If your organization receives funds from more than one Federal source during the year for which the audit is conducted, an organization-wide audit must be performed. (Note that CPB funding is not considered a Federal source.)

    If an allowance for audit costs was included in your Grant Award, the audit report must be submitted prior to the deadline for submitting the close-out documentation in order for the cost to be charged to the grant.

    Questions about audits should be addressed to your Grants Specialist in the Grants & Agreements Management Division.


    Priority Lien Requirements

     

    The Federal government retains a priority reversionary interest in all equipment you acquire as part of the project. The Federal interest extends from the initial receipt of the equipment through a ten-year period after the project is completed. This interest is secured through a lien document.

    You may have been required to file an initial lien at the start of your Grant Award Period. This lien may have been revised to reflect amendments to your approved equipment list during the Grant Award Period. Regardless of the number of lien documents you may have filed during the Grant Award Period, you are required to submit a completed lien form as part of the close-out documentation.

    • This lien must cover all equipment included on the approved final inventory.
    • This lien must show precise information about each item of equipment acquired, including:
      • manufacturer, model, and model number;
      • how many of each item was acquired;
      • manufacturer's serial number;
      • your organization's inventory number; and
      • cost.
      These things are shown by attaching a copy of the approved final inventory to the lien form and incorporating it into the lien by reference (see below).

    It would be premature for you to submit a fully-recorded final lien with the close-out documents, because PTFP has to approve the final inventory attached to the lien and GAMD must sign the form before it is recorded. Even if the lien form in your state does not require a signature by the secured party, you must submit the form with the attached inventory for PTFP and Grants Office approval before you file it.


    Uniform Commercial Code (UCC) Forms

    Most grantees use UCC (Uniform Commercial Code) forms for the final lien. In some states a chattel mortgage is used. UCC forms differ slightly from state to state. They are usually available from an attorney, from a bank's loan department, or from an office supply store.

    If required, an initial lien is usually submitted on a UCC-1 form. Subsequent lien forms that revise the equipment list are usually done as an amendment to the original lien and are prepared on whatever form is required in your state.


    Completing the UCC Form

    Whether the lien submitted with the close-out is your first or not, follow the guidelines below for completing the form.
    (1) Enter your organization's name and address as the "Debtor".

    (2) Enter the following in the section for the "Secured Party":

       NTIA/PTFP
       Room H-4812
       U.S. Department of Commerce
       1401 Constitution Avenue, NW
       Washington, DC 20230

    (3) In the section designated for the description of the items covered by the lien, enter the following:

    This financing statement covers all equipment purchased under National Telecommunications and Information Administration Grant No. [enter complete grant number; e.g., 33-01-33333] A copy of the project's equipment list is attached and is incorporated into this lien by reference. The term of this priority lien shall extend for a period of ten years following [fill in the project expiration date or the date on which project completion is certified if the project is completed before the end of the Grant Award Period], during which time the Federal Government retains a priority reversionary interest in the equipment on the attached list.

    (4) The lien document should be signed as the "Debtor" by the official of your organization authorized to sign liens and sent to PTFP as part of the package of close-out documents. Attach a copy of the final inventory of equipment submitted for PTFP review to each lien form prepared.

    After review by NTIA/PTFP, the Grants & Agreements Management Division (GAMD) will sign the lien document for the "Secured Party" and return it to you. You must then file it at recorder(s) office(s) in the jurisdiction(s) where the project equipment will be located and where your headquarters are located, if different. This may require the preparation of more than one lien document.

    Once filed, the secured party's copy of the lien, with the recording office stamp clearly visible, must be returned promptly to:

    
    	[Grants Specialist's Name]
    National Institute of Standards and Technology
    Office of the Chief Financial Officer
    Grants & Agreements Management Division
    100 Bureau Drive, Mail Stop 3580
    Gaithersburg, MD  20899-3580
    
    

    Please submit an original and one photocopy of

    each lien form required by your project.


    FCC Documents

     

    When Federal Communications Commission (FCC) authorization is required for a grant project, the authorization is usually the subject of a Special Award Condition placed in the Grant Award document and worded along the following lines:

      No funds from the Federal share of this grant award shall be released until the recipient has secured all Federal Communications Commission (FCC) authorizations required by the grant project and has provided copies of the FCC documents to the NTIA.

    If you have already supplied FCC authorizations to NTIA/PTFP to fulfill a Special Award Condition, you need not resubmit the documents as part of the Close-Out. Your Program Officer will let you know if additional FCC documents are required.


    Site Rights

     

    As indicated in the section on liens, the Federal government has an interest in PTFP-funded equipment for ten years after the completion of a project. To ensure that inadequate site rights will not hinder your ability to provide long-term public telecommunications services, you may be required by NTIA/PTFP to provide evidence of leases or ownership of sites on which major fixed pieces of equipment are located.

    When site rights certification is required, it is usually requested in a Special Award Condition placed in the award document and stated in language similar to the following:

      No funds from the Federal share of this grant award shall be released until the recipient provides to NTIA an opinion letter from its attorney describing the ownership or leasehold interest the recipient has in all sites on which the recipient will locate major fixed equipment, such as broadcast transmitters or towers (whether or not funded by this grant project). The attorney's opinion letter shall comply with the requirements provided by the NTIA. If the recipient fails to submit the required certification letter by March 31, 2XXX, this grant award may be terminated.

    If you have already supplied the necessary opinion letter to NTIA/PTFP to fulfill a Special Award Condition for site rights, you need not re-submit it as part of the Close-Out. Your Program Officer will contact you if additional material is required.


    Construction Grant Close-Out Checklist

     

    Supply an original and one copy of all documents except the lien form, with the full grant number (e.g., 99-01-99999) and original signatures where required on both copies. Attach a copy of the inventory to each lien document, and please include a photocopy of each lien document.

    Grant Award Number: ___________________________________
    Grant Award Start Date: ___________________________________
    Grant Award Ending Date: ___________________________________
    Extended to: ___________________________________
    Close-Out due: ___________________________________
    Grant Amount: ___________________________________
    Local Matching Share: ___________________________________
    Total Project Cost: ___________________________________


        DUE   SENT
    Certification of Completion   ____________   ____________
    Final Inventory ____________ ____________
    Lien (with copy of inventory attached) ____________ ____________
    Site Certification (if required)   ____________   ____________
    FCC Documents (if required) ____________ ____________

    PTFP Program Officer:    _________________________________
    (Phone: 202/482-5802)

    GAMD Grants Specialist:   _________________________________
    (Phone: 202/482-1370)


    Review of Close-Out Documents

    NTIA/PTFP reviews all close-out documents to be sure that the project was completed in accordance of the terms and conditions of the award. The program may request clarification or revision of material submitted in your package of close-out documents. Your prompt response will assist in the timely completion of the close-out process.

    All grant recipients should be aware that failure to provide additional requested close-out information in a timely manner can result in

    • the establishment of an Account Receivable for all Federal funds paid to your organization and
    • the denial of future grants to your organization.


    Final Inventory

     

    Items included on the final inventory and not approved for purchase in the Financial Assistance Award document or in a subsequent amendment will be removed from the final approved inventory. This may result in a requirement to refund Federal funds already paid to your organization.

    It is worth repeating something said earlier: inventories will not be amended retroactively as part of closing out a grant in order to cover items purchased without prior written authorization from the National Institute of Standards and Technology, Grants & Agreements Management Division.


    The Federal Interest Period

    Your responsibility to the Federal government through the Department of Commerce does not end when the National Institute of Standards and Technology, Grants & Agreements Management Division informs you that your close-out has been completed. This section summarizes some of the requirements imposed on grantees in the years after a grant is closed out.


    Retention of Records

     

     

    Federal regulations require that your organization keep financial records, supporting documents, statistical records, and all other records pertaining to the grant project for three (3) years after your final financial status report has been accepted. If any litigation, claim, or audit is started before the expiration of the three-year period, all records must be kept until all litigation, claims, or audit findings involving the records have been resolved. Grant recipients must keep the following records intact and accessible for inspection at any time:

    (1) A complete and itemized inventory of all public telecommunications facilities under the control of the grantee, whether or not financed, in whole or in part, with Federal funds;
    (2) Complete and current financial records that fully disclose the total amount of the project; the amount of the grant; and the amount, nature and sources of all non-Federal funds associated with the project; and
    (3) All records specified in Office of Management and Budget Circular A-110 (for educational institutions, hospitals, and non-profit organizations) and 15 CFR Part 24 (for state and local governments).

    Project equipment must be marked in a permanent manner to assure easy and accurate identification and reference to inventory records. The marking includes the PTFP grant number and a unique inventory number assigned by the grantee.



    Inspections

     

     

    Grantees must permit inspections at any time during normal business hours by NTIA and the Comptroller General of the United States, or their authorized representatives, of the public telecommunications facilities acquired with Federal financial assistance and of any books, documents, papers, and records relating to those facilities.


    Annual Status Reports for Construction Grants

     

     

    Organizations that have received construction grants from NTIA/PTFP are required to submit an Annual Status Report for every grant project that is in the Federal interest period. By statute, this is the 10-year period during which the Federal government retains a reversionary interest in all equipment purchased under the project. The Federal interest period begins with the project completion date, as established by NTIA/PTFP during the close-out procedure.

    Annual Status Reports are due on or before April 1 in each of the ten years of a grant's Federal interest period. If you have more than one grant to report on, you may submit a single report as long as it shows clearly the full grant number of each award you have in the 10-year Federal interest period.

    In a conspicuous space at the beginning, the report should be identified as an Annual Status Report, with the full, nine-digit PTFP grant number (e.g., 99-01-99999).

    In the Annual Status Report, the grant recipient must certify:

    Mark for List Item That it remains an eligible entity, as defined in the PTFP Rules.
    Mark for List Item That it continues to use the equipment purchased under the grant for the original purposes of the grant.
    Mark for List Item That it continues to possess all FCC authorizations necessary for the project.
    Mark for List Item That all equipment purchased under the grant continues to be protected by adequate insurance coverage. [Note: You are no longer required to submit a certificate from your insurance carrier or risk manager.]
    Mark for List Item That it remains in compliance with all of the terms and conditions of the grant. If the grant was awarded before FY 1988, then the terms and conditions are stated in the PTFP Rules (see 15 CFR 2301.28 [1985-87]). If the grant was awarded in FY 1988 or thereafter, the terms and conditions are found in Part V of the application form, "Assurances" (contained in Attachment B for applications filed during FY 88-90). Beginning with the FY 1988 grant awards, these assurances are fully incorporated into the Financial Assistance Award document as the grant's terms and conditions at the time the grant is awarded.
    Mark for List Item That no significant changes have occurred during the reporting period with respect to any of the terms and conditions of the grant. Or that changes have occurred (for example, has the recipient experienced any significant change in its corporate structure?). Any such changes must be reported.
    Mark for List Item The recipient must provide information as to whether any discrimination complaints are pending against it and whether any recent adverse judgments have been rendered against it because of discriminatory practices. If a discrimination complaint is pending, the recipient should provide a brief description of the complaint and its status. If any adverse judgment has been rendered, the recipient should summarize that judgment and describe what affirmative action has been taken or is being taken to remedy the effects of the adjudged discrimination.
    Mark for List Item If the recipient is a state or municipal agency, non-profit institution, or a college or university, then discrimination complaints and recent adverse judgments must be reported for the entire organization -not just for the radio or television station. However, state or municipal agencies should report discrimination complaints/adverse judgments only for the agency that actually receives the Federal grant money, not the entire state or municipal government.
    Mark for List Item IF THE RECIPIENT IS AN ACADEMIC INSTITUTION, it must certify that the institution will not discriminate in its admissions policies nor in the opportunities it affords to persons to participate in the receiving or providing of services. This certification is applicable to the entire academic institution, not just to the entity (usually, as noted above, a radio or TV station) that was the subject of the grant.

    The Annual Status Report should be signed by an official of the recipient organization who is legally authorized to make such certifications for it. In a college or university, this is often the president or the head of the grants and contracts office. A nonprofit institution will often have its president sign.

    Annual Status Reports should be sent to the following address:
    	
    		William Cooperman, Director
    		Public Broadcasting Division
    		National Telecommunications and Information Administration
    		U.S. Department of Commerce
    		1401 Constitution Avenue, N.W., Room H-4812
    		Washington, D.C.  20230

    A SAMPLE ANNUAL STATUS REPORT APPEARS BELOW TO ASSIST YOU IN
    PREPARING YOUR REPORTS


    Sample Annual Status Report Letter

    William Cooperman
    Director
    Public Broadcasting Division
    National Telecommunications and Information Administration
    U.S. Department of Commerce
    1401 Constitution Avenue, N.W., Room 4812
    Washington, DC 20230

    Subject:   Annual Status Report: April 1, 2XXX - March 31, 2XXX
        PTFP Grant #99-02-99999
        Station KBBB-TV
        Eastern State University
        Anytown, State 00000

    Dear PTFP Director:

    With respect to the above-referenced grant, we hereby certify the following:

    • That Eastern State University remains an eligible entity as specified in the PTFP Rules and Regulations.
    • That the equipment purchased under the grant continues to be used for the original purposes of the grant.
    • That Station KBBB continues to have all FCC authorizations necessary for the grant project.
    • That all equipment purchased under the grant continues to be protected by adequate insurance coverage.
    • That Eastern State University remains in compliance with all the terms and conditions of the grant.
    • That no changes have occurred during this reporting period with respect to any of the terms and conditions of the grant.

    Sincerely,

    Thomas A. Anyone
    President

    Continuation of the Lien


     

    PTFP construction grant recipients are required to take steps to ensure that the Federal government's position as primary secured creditor is fully protected for the entire 10-year period of Federal interest. This protection is secured by a lien document, generally a UCC-1 financing statement, the final version of which is recorded during the grant close-out procedure.

    Many states, however, do not extend such protection through the Federal interest period under a single lien document. In those states, continued protection is secured by recording a continuation statement. Recognizing the need for and recording of continuation statements is your responsibility. If you are located in any state except those listed below, you must continue to protect the Federal interest by filing a continuation of the final lien at the appropriate interval(s).

    All states require renewal of the lien after five years, with the following exceptions:

      Arizona   6-year term
      Maryland   12-year term
      Tennessee   20-year term
      Louisiana   no time limit
      Puerto Rico   no time limit
      Guam   NTIA has no information
      American Samoa   NTIA has no information

    Recognizing the need for, preparing, and recording continuation documents is your responsibility. To help you with this, we suggest that you enter the date the lien was recorded ("stamped") on the checklist that follows.


    Checklist for Federal Interest Period
      Grant Award Number: _____________________________
      Beginning of the 10-year  
      Federal interest period: _____________________________
      Date Final Lien filed: _____________________________
      Lien expiration date: _____________________________
      Certified copy to GAMD: _____________________________
      Lien continuation filed: _____________________________
      Copy sent to PTFP: _____________________________

    Annual Status Report Filings
       
    DUE
    SENT
      First year April 1, 20__ ____________
      Second Year April 1, 20__ ____________
      Third Year April 1, 20__ ____________
      Fourth Year April 1, 20__ ____________
      Fifth Year April 1, 20__ ____________
      Sixth Year April 1, 20__ ____________
      Seventh Year April 1, 20__ ____________
      Eight Year April 1, 20__ ____________
      Ninth Year April 1, 20__ ____________
      Tenth Year April 1, 20__ ____________