Except for lien documents, please get in the
habit of submitting to PTFP all reports, supporting documentation,
and other items that may be requested in duplicate! |
| |
Please always put your full grant number--e.g.,
99-99-N99999 - on anything you send to PTFP or NIST/GAMD. |
The Construction Schedule is the timetable of how you plan to complete your project. All equipment must be installed and operational, and all expenditures approved for the project must be incurred by the end of the Grant Award Period. As you prepare your Construction Schedule, you should anticipate and allow for normal delays that may happen in a project of your kind.
As you prepare your Construction Schedule, please
keep in mind that your project was funded because of the urgency of need
expressed in your application. Completion of the project should reflect
the same sense of urgency. Your organization is expected to begin work
on the project promptly and to complete it within the Grant Award Period
specified in the award document.
NTIA has found that the greatest single cause of the
inability of grantees to complete their projects within the authorized
Grant Award Period is a delay in the start of equipment procurement. If
you anticipate a delay of more than a few weeks while equipment is researched
for the writing of bid specifications, please discuss the matter with
your Program Officer as you prepare your Construction Schedule.
You can prepare your Construction Schedule online through
PORTS . It is due at PTFP thirty
(30) days after the start-date on page 1 of your grant award (CD-450). If you prepare it in hardcopy rather
than in PORTS, please send two copies to PTFP.
Your Construction Schedule must be sufficiently detailed
to allow PTFP to be sure that all necessary steps to complete the project
are planned and scheduled and also to allow it to track progress as the
project goes forward. If you prepare your Construction Schedule online, PORTS provides a matrix to be filled in.
The Construction Schedule should contain projected
dates for the following items:
- When advertising for bids on equipment items
will begin.
- The deadline for the receipt of bids.
- When purchase orders/contracts for equipment will
be issued.
- When installation of equipment will begin.
- When installation will be completed.
- When testing of the grant equipment will begin.
- When testing will be completed.
- When all equipment authorized in the grant will
be operational.
- When you expect to submit requests for payment,
with an estimate of the amount to be requested in each payment.
- When the following documents will be submitted
to NTIA/PTFP if required by a Special Award Condition in the award
document:
- The initial lien.
- Evidence of insurance.
- Attorney's letter certifying the site
rights (due six months after the start of the Grant Award Period).
- Auditor's certification regarding financial
management system (This one goes to NIST/GAMD).
- Any document(s) needed to comply with a Special
Award Condition that is unique to your project
(There may be other Special Award Conditions, depending upon the circumstances
of your project. If so, they may require your action by a specified
date. Be sure these response dates are included in your Construction
Schedule.)
When the Close-Out will be submitted.
Any other important information affecting the
speedy completion of the project.
As noted above, you can prepare your Construction Schedule online
through PORTS. If you prepare it in hardcopy, please submit it to PTFP in duplicate.
As noted in the Introduction, above, we recommend that you keep a printed copy of your Construction
Schedule at hand to refer to as a kind of checklist as the projects prodeeds.
|
Sample
Construction Schedule
|
| Anytown State University |
NTIA/PTFP Grant
No. 99-99-N99999 |
| Anytown, State |
Station WPS (FM) |
CONSTRUCTION SCHEDULE
| Project start date |
10/01/XX |
|
| Mail construction schedule |
10/08/XX |
|
| Prepare specs for transmitter |
11/05/XX |
|
| Prepare specs for studio equipment |
11/19/XX |
|
| Request for bids on transmitter |
12/14/XX |
|
| Mail initial lien |
12/16/XX |
[include only if specified in award
document] |
| Mail insurance certification |
12/16/XX |
[include only if specified in award
document] |
| Request for bids on studio equipment |
12/21/XX |
|
| Open bids for transmitter |
1/18/XX |
|
| Mail Quarterly Performance Report |
1/21/XX |
|
| Open bids for studio equipment |
2/04/XX |
|
| Award transmitter contract |
2/08/XX |
|
| Award studio equipment contract(s) |
2/22/XX |
|
| Special Award Condition: Site Rights |
3/20/XX |
[include only if specified in award
document] |
| Mail SF-269 Long Form to NIST/GAMD |
4/12/XX |
|
| Mail Quarterly Performance Report |
4/19/XX |
|
| Begin studio equipment installation |
4/19/XX |
|
| First payment request: $20,000 |
4/28/XX |
|
| Studio equipment installation complete |
5/19/XX |
|
| Second payment request: $10,000 |
5/24/XX |
|
| Begin transmitter installation |
5/31/XX |
|
| Third payment request: $40,000 |
6/07/XX |
|
| Mail Quarterly Performance Report |
7/17/XX |
|
| Transmitter testing begins |
7/26/XX |
|
| Transmitter installation completed |
8/18/XX |
|
| Final payment request: balance |
8/23/XX |
|
| Grant Award Period ends |
9/30/XX |
|
| Mail Quarterly Performance Report |
10/16/XX |
|
| Mail Close-Out |
12/15/XX |
|
Your award document may contain Special Award Conditions
that require the submission of documents to NTIA/PTFP before Federal funds
are released to your organization. Such Special Award Conditions are generally
printed at the end of the award document. They usually begin: "No funds
from the Federal share of this grant award shall be released until the
recipient has submitted to NTIA...".
The most common Special Award Conditions
relate to liens, insurance coverage, site rights, FCC authorizations,
your organization's financial management system, the
Internal Revenue Service, and consultants and/or contractors. These are
discussed in order below, but other Special Award Conditions
may be included in the Grant Award as circumstances require. Please note
that the Department of Commerce may impose Special Award Conditions at
any time during the grant award period.
For each Special Award Condition:
Note that many of the documents required to meet the Special Award Conditions can be
submitted electronically as attachments in PORTS, via e-mail, or by fax to PTFP (202-482-2156).
NTIA/PTFP retains a priority reversionary
interest in all equipment acquired pursuant to the project. The interest
extends from the beginning of the Grant Award Period through a ten-year
period following the completion of the project. Some grantees are required
to file an initial lien for their projects. If one is required, Federal
funds cannot be released until the lien has been submitted, approved,
filed, and a certified copy returned to NIST/GAMD.
When an initial lien is required for a PTFP
project, it is usually requested in a Special Award Condition placed in
the award document and stated in language similar to the following:
| |
No funds from the Federal share
of this grant award shall be released until the recipient has executed
and recorded a document establishing that the Federal government has
a priority lien on any facilities purchased with funds under this
award during the period of continuing Federal interest.
|
Most grant recipients use a UCC-1 (Uniform
Commercial Code) financing statement. A chattel mortgage may also be used.
UCC-1 forms differ slightly from state to state. They are usually available
from an attorney, a bank's loan department, or an office supply store.
Completing the UCC-1
Enter your organization's name and address
as the "Debtor". Enter the following in the section for the "Secured Party":
NTIA/PTFP
Room 4812
U.S. Department of Commerce
1401 Constitution Avenue, NW
Washington, DC 20230
In the section designated for the description
of the items covered by the lien, enter the following:
| |
This financing statement covers all equipment
to be acquired under National Telecommunications and Information Administration
Grant No. [enter complete grant number; e.g., 99-99-N99999].
A copy of the project's equipment list is attached and is incorporated
into this lien by reference. The term of this priority lien shall
extend for a period of ten years following [fill in the project
expiration date from the face sheet of the award document], during
which time the Federal Government retains a priority reversionary
interest in the equipment on the attached list. |
Attach a copy of the approved equipment list from your
award document. The lien document should be signed as the "Debtor" by your
organization's Certifying Representative (if a signature is required by your state) and sent to PTFP at
the following address:
[Name of your organization's PTFP Program Officer]
NTIA/PTFP
Room 4812
U.S. Department of Commerce
1401 Constitution Avenue, NW
Washington, DC 20230
The PTFP Program Officer will review the lien and
forward it to the National Institute of Standards and Technology (NIST),
Grants and Agreements Management Division (GAMD). (Note that the lien form must be sent to
PTFP before filing, even if your state's form does not include a space for the Secured Party
to sign it.) NIST/GAMD will sign the lien document for the "Secured Party" and return it to you.
You must then file it at recorder(s) office(s) in the jurisdiction(s)
where the project equipment will be located and
where your headquarters are located, if different.
Original lien forms, with the recording office's
stamp clearly visible, must be returned promptly to:
[Grants Specialist's Name]
National Institute of Standards and Technology
Office of the Chief Financial Officer
Grants & Agreements Management Division
100 Bureau Drive, Mail Stop 1650
Gaithersburg, MD 20899-1650
Additional Liens
You may be required to provide revised liens prior to
the completion of your project if your grant award is amended to include
additional or materially different equipment.
In many jurisdictions, the lien can be revised by
executing an amendment to the original UCC-1. The forms to amend the original
filing have different designations in various jurisdictions. In many states,
the amendment version is called a UCC-2 or a UCC-3.
Follow the same procedures to file a revised UCC form
as outlined for the initial lien.
All grantees are required to maintain adequate insurance
coverage on the equipment purchased under a PTFP grant so that, in the
event of loss, they will be able to continue the project by promptly replacing
equipment.
Some grant awards include a Special Award Condition
for insurance coverage. If yours does, your organization must certify
that all equipment to be purchased with PTFP funds will be insured. When
an insurance certification is required for a PTFP project, the Special
Award Condition is usually stated in language similar to the following:
| |
No funds from
the Federal share of this grant award shall be released until the
recipient has certified that the grantee maintains protection against
common hazards through adequate insurance coverage or other equivalent
undertaking, except that, to the extent the grantee follows a different
policy of protection with respect to its other property, the grantee
may extend such policy to apparatus acquired and installed under the
project. The grantee shall certify that it has purchased flood insurance
(in communities where such insurance is available) if the facilities
will be constructed in an area that has been identified by the Federal
Emergency Management Agency as having special flood hazards. Certification
shall be in the form of a letter signed by the Chief Executive Officer,
Chief Financial Officer, or Risk Manager of the recipient organization. |
As indicated in the section on liens, the Federal
government has an interest in PTFP-funded equipment for ten years after
the completion of a project. To ensure that inadequate site rights will
not hinder a grantee's ability to provide long-term public telecommunications
services, NTIA requires grantees to have adequate rights to each site
on which such items of major fixed equipment as a broadcast transmitter
or a tower are or will be installed. Some grant recipients are required
by NTIA/PTFP to provide evidence of leases or ownership of such sites.
When site rights certification is required for a PTFP
project, it is requested in a Special Award Condition placed in the award
document and stated in language similar to the following:
| |
No funds from
the Federal share of this grant award shall be released until the
recipient provides to NTIA an opinion letter from its attorney describing
the ownership or leasehold interest the recipient has in all sites
on which the recipient will locate major fixed equipment, such as
broadcast transmitters or towers (whether or not funded by this grant
project). The attorney's opinion letter shall comply with the requirements
provided by the NTIA. If the recipient fails to submit the required
certification letter by [date], this grant award may be terminated. |
As stated in the Special Award Condition, if the required
attorney's certification letter regarding the site rights is not submitted
to NTIA/PTFP in final form by the deadline stipulated, the grant award
may be terminated. Grantees should work with their local attorneys to
develop acceptable lease or ownership agreements. NTIA expects grantees
to have at least the following for a ten-year period at each site involved:
- The right--whether by fee simple title, appropriate
long-term lease, or the option or rights of renewal to obtain the same--to
occupy the site(s).
- The right to construct, maintain, operate, inspect,
and remove the project equipment without any impediments in the site
contract(s) or local zoning laws, or any other known impediments.
In addition, nothing under local law or enforceable
contract should prevent the Federal government from entering the property
and reclaiming or securing grant-funded property.
Exceptions
The letter should address specifically any exceptions
to the general provisions above and to the statements in the sample letter
below. It should identify and fully explain any circumstances that support
the conclusion that those exceptions do not materially interfere with the
grantee's and the Federal government's ability to protect the grant property
and the continued operation of the project for the duration of the Federal
interest period.
If your rights are subject to restrictions that might
prevent occupancy for the full ten-year period, your counsel must certify
that the Federal interest in the equipment is fully protected. For example,
a lease may allow the lessor to terminate occupancy in certain events
(non-payment or other default), or its term may be less than the full
ten years (without a renewal clause). In these situations, counsel must
certify that:
| (a) |
If the lease allows the lessor unilaterally
to terminate the lease for cause and evict the lessee, the lessor
must provide adequate advance notice in writing of such action. Preferably,
the lease will provide reasonable opportunity to "cure" problems,
and sufficient time to relocate the facilities without a break in
the broadcast service. The requisite period of time may vary with
the nature of the facility and local real estate market, but the advance
notice period would typically be 60 to 120 days. |
| (b) |
A lessor's lien, if any, on the grant-funded
property remains subordinate to the Federal lien on the property.
A lessor's right, if any, to remove property in an eviction situation
is subject to an obligation to hold and to protect that property for
disposition by the Federal government. |
| (c) |
If the lessor has rights that exceed
those outlined in (a) or (b), above, or has other rights that interfere
with the operation of the project (such as termination of needed services),
local law or enforceable contract ensures that these rights are exercised
reasonably. Reasonableness includes adequate prior notice to the grantee
and cooperation or consultation with the grantee to minimize damages. |
A SUGGESTED LETTER
OF CERTIFICATION:
(ATTORNEY LETTERHEAD)
NTIA/PTFP Grant No.:__________
I, (attorney name), certify that
I am legal counsel to (grantee name) and that it has major fixed
equipment at the following site(s):
| Site |
|
|
Use of Site |
Status |
Lessor Name |
| |
|
|
[Transmitter, microwave, etc.] |
[Own, lease,option] |
|
I recognize that the Federal Government has an interest
in the project from the award date through a period ten years after project
completion. For [each of]
the above site[s],
I certify that, during the Federal interest period:
- The grantee has the right by [fee simple title,
appropriate long-term lease, or the option or rights of renewal to obtain
the same] to occupy the above site[s]
- The grantee's right to construct, maintain, operate,
inspect, and remove the project equipment is not subject to any impediments
in the site contract[s] or local zoning laws, or any other
known impediments.
- Under local law or enforceable contract, nothing
prevents the Federal government from entering the property and reclaiming
or securing grant-funded property.
[Discussion of any possible exceptions].
Signature of legal counsel
|
We
would like to emphasize what is NOT necessary. NTIA does not
require that the recipient's attorney conduct a title search. Nor
does NTIA expect that the attorney will perform research into the
real estate laws and zoning regulations of the communities in which
the project's major fixed equipment is located. In fact, no
special research should be called for to satisfy this Special Award
Condition. NTIA merely expects that the attorney will read carefully
the site document in question and, based upon that reading, determine
whether the document conforms to NTIA's requirements. Attorneys
may, if they choose, state the limitations of their research in
the opinion letter.
|
If your project requires authorization from the Federal Communications Commission before it can be built and you did not have that
authorization in hand when your PTFP application was negotiated, a Special Award Condition was imposed stating that no Federal funds can be released until the necessary
authorization has been issued and copies supplied to NTIA/PTFP. When a project is very large and requires a number of FCC authorizations, the Special Award Condition may be
worded to allow Federal funds to be released for different portions of the project as the various authorizations are issued by the Commission.
You should keep your PTFP Program Officer informed about the status of your FCC application and any actions the Commission takes apart from issuing
a required authorization. Please note, however, that NTIA/PTFP cannot intervene on behalf of your organization with the FCC.
This condition--imposed by the National Institute of Standards and Technology (NIST), Grants and Agreements Management Division (GAMD)-- requires that a Certified Public
Accountant certify that your organization's financial management system
meets the requirements and standards prescribed in 15 CFR Part 14, Subpart C, Section 14.21. The certification should be sent to your
Grants Specialist in NIST/GAMD, not to your PTFP Program Officer. (See under
"
Housekeeping Items," for the address of
NIST/GAMD.)
If the Internal Revenue Service (IRS) had not ruled
on your organization's non-profit status when you submitted your PTFP
application or when that application was negotiated, a Special Award Condition
was imposed:
| |
No funds from the Federal share of this
grant shall be released until the recipient has submitted to the NTIA
a copy of the Internal Revenue Service certification of its non-profit
status. |
To meet this condition, send your Program Officer
two copies of the IRS certification.
This condition is imposed only on planning grants.
Most such projects make use of consultants or contractors to perform some
or all of the studies required for the project. Two copies of the resume(s)
and/or proposal(s) of any such consultants and contractors must be submitted
to PTFP for approval before the project may proceed. The materials should
be sent to your PTFP Program Officer.
Please note that this condition is in addition to
the consultant/contractor requirement stated in the applicable OMB circulars.
All acquisitions made as part of an NTIA/PTFP
grant must be done through open competitive bidding. As the Office of
Management and Budget puts it, "All procurement transactions shall be
conducted in a manner to provide, to the maximum extent practical, open
and free competition." NTIA strongly urges you to avoid time-consuming
and costly disputes with potential contractors and vendors by familiarizing
yourself with the rules and procedures governing competitive bidding.
Among the many points to consider are the following:
- In the award document, Special Award Condition
Number 10 for planning projects and Number 11 for construction projects.
- Read carefully--and have your procurement officer
read carefully--the rules and regulations about competitive bidding
of both your state and the Federal government. Federal purchasing regulations
are contained in 15 CFR 24, which was included in the packet of award
documents. If you do not have copies of these regulations, make
certain that you acquire and read them before you put
any items out to bid.
- You may not subgrant any funds or contract
with any organization that has been excluded from, or is ineligible
for, participation in Federal assistance programs. The Federal Excluded Parties System can be accessed at www.epls.gov.
- When you purchase any item as part of
the grant project, be certain that you follow all Federal procurement
guidelines, as well as any state guidelines and procedures to which
your organization is subject.
- Take special care to make clear to prospective
bidders the code of standards they are to follow, as spelled out in
the OMB circular.
- All procurement transactions must be
handled competitively. Practices that may result in restrictive bidding
include the following:
- placing unreasonable requirements on prospective
bidders;
- requiring unnecessary experience or excessive
bonding;
- engaging in organizational conflicts of interest;
and
- specifying a brand name product, or describing
the item to be procured in such a way that all but one manufacturer
are excluded. When a "brand name or equal" description is used, the
specifications should state the specific features of the brand name
product that bidders must meet.
| ** |
Specifications are best
set forth in terms of functions to be performed or the performance
required. Specifications probably are restrictive if they specify
how a given function must be carried out
and only one manufacturer's equipment does it that way. Copying specifications
supplied by a vendor or manufacturer is almost certain to provoke
a bid protest unless that vendor or manufacturer is excluded
from bidding. A bid protest can result in a time-consuming, lengthy
delay in completing your grant project and may cause a delay in your
ability to draw grant funds. Awarding a purchase contract to the low
bidder does not "prove" that restrictive bid specifications were not
used. |
- Maintain detailed records
relating to all procurement. Be especially careful to document:
- the rationale for the procurement,
- the reason why a particular bid was
rejected, and
- the reason why a particular bid was
accepted.
- In the event of a protest on any bid
specification, make certain that you are aware of all the local
administrative remedies available to you within your organization and
state for resolving bid protests.
Please do not automatically refer bid
protests to the Federal government for resolution. The Federal
government limits its role in resolving bid protests to cases in which
violations of Federal law or regulations have occurred, and/or the recipient's
organization has failed to review the complaint properly.
It is your responsibility to learn what you can and
cannot do with regard to bidding procedures.
Quarterly Performance Reports (sometimes called Quarterly Technical Reports) are due at PTFP within thirty days after the end of each calendar quarter. The Reports let PTFP and NIST/GAMD follow your progress in completing your project.
The dates the Quarterly Performance Reports are due
at PTFP are as follows:
| |
For the Quarter |
|
Your report is due
at PTFP
|
| |
October 1 to December 31 |
|
no later than January 31 |
| |
January 1 to March 31 |
|
no later than April 30 |
| |
April 1 to June 30 |
|
no later than July 31 |
|
July 1 to September 30 |
|
no later than October 31 |
The Construction Schedule submitted at the start of the project should serve as the matrix for your Reports whether prepared online through PORTS or on paper. As shown in the sample below, if dates on your Construction or Planning Schedule are not met, you should show a revised date in the column provided with an explanation for the revision in the appropriate place.
Reports should show the complete PTFP grant number, be identified as a Quarterly Performance Report, and state the reporting period. Reports are expected to include the following:
- Comparison of actual accomplishments
during the reporting period with the goals established in the Construction
or Planning Schedule for that reporting period.
- Description of any problems that have
arisen or reasons why the established goals have not been met.
- Actions taken to remedy any failures
to meet goals.
- List of equipment purchased during the
reporting period compared with the equipment authorized in the award
document. This information should include:
- brief description of each item,
- manufacturer and model number,
- quantity of each item purchased, and
- cost.
As indicated, your Quarterly Performance Report should include a list of the equipment purchased through the current quarter compared with the equipment authorized in the grant. Online, PORTS supplies the list. The left-hand column shows what was authorized. You should use the right-hand column to supply information on the equipment actually purchased as you acquire it. The list should be cumulative through the project so that it shows NTIA/PTFP all that has been acquired through the most recent Quarterly Performance Report. If you prepare your Report offline, you should utilize the actual equipment pages from the award document. (See the example below.)
While the equipment list and narrative should reflect
the current status of the project, NTIA is not seeking a complete history
of the project in each quarterly report. Information for the current reporting
period should be highlighted, which can be done simply with an ***.
When you address pending issues from prior quarters, you should condense
the prior information and emphasize the updated material. Items on the
Construction or Planning Schedule that have been fully completed can be
reported simply as "Completed".
Using the format shown here will help you, your Program Officer, and your Grants Specialist follow your progress in completing the project.
| Anytown State University |
|
NTIA/PTFP Grant No.
99-99-N99999 |
| Anytown, State |
Quarterly Performance
Report |
Station WPS (FM) |
| |
Period Ending March 31, 20XX - Prepared
April 19, 20XX |
|
| Construction Schedule Activity |
|
Original |
|
Revised |
|
Completed |
|
Report Remarks |
| Project start date |
|
10/01/XX |
|
|
|
10/01/XX |
|
|
| Mail construction schedule |
|
10/09/XX |
|
|
|
10/09/XX |
|
Completed. |
| Submitted Amendment Request |
|
|
|
|
|
10/09/XX |
|
Requested approval to substitute
RDAT recorders for the reel-to-reel machines in the Grant Award. |
| Prepare specs for transmitter |
|
11/05/XX |
|
11/19/XX |
|
11/16/XX |
|
Completion of specs delayed by illness.
No significant effect on project. |
| Prepare specs for studio equipment |
|
11/19/XX |
|
|
|
11/30/XX |
|
Approval of amendment request to
change to RDAT recorders received November 27. Project should still
be completed on time. |
| Request for bids on transmitter |
|
12/14/XX |
|
12/28/XX |
|
12/24/XX |
|
Completed. |
| Mail initial lien |
|
12/16/XX |
|
|
|
12/17/XX |
|
Completed. |
| Mail insurance certification |
|
12/16/XX |
|
|
|
12/17/XX |
|
Completed. |
| Request for bids on studio equipment |
|
12/21/XX |
|
|
|
12/28/XX |
|
Completed. |
| Open bids for transmitter |
|
01/18/XX |
|
|
|
01/28/XX |
|
Completed. |
| Mail Quarterly Performance Report
|
|
01/21/XX |
|
|
|
01/21/XX |
|
Completed. |
| Open bids for studio equipment |
|
2/04/XX |
|
|
|
2/08/XX |
|
Completed. |
| Award transmitter contract |
|
2/08/XX |
|
|
|
2/15/XX |
|
Transmitter contract awarded to American
Transmitter Corp., with delivery expected in 90 days. |
| Award studio equipment contract(s) |
|
2/22/XX |
|
2/29/XX |
|
3/01/XX |
|
Slight delay due to amendment request.
Contracts awarded to Midtown Electronics, Inc., and Technical Supply
Co. Delivery expected in 45 to 60 days. |
| Special Award Condition: Site Rights |
|
3/20/XX |
|
|
|
3/20/XX |
|
Completed. |
| Mail SF-269 to NIST/GAMD |
|
4/12/XX |
|
|
|
|
|
|
| Mail Quarterly Performance Report
|
|
4/19/XX |
|
|
|
|
|
|
| Begin studio equipment installation
|
|
4/19/XX |
|
4/28/XX |
|
|
|
|
| First payment request: $20,000 |
|
4/28/XX |
|
|
|
|
|
|
| Studio equipment installation complete |
|
5/19/XX |
|
|
|
|
|
|
| Second payment request: $10,000 |
|
5/24/XX |
|
|
|
|
|
|
| Begin transmitter installation |
|
5/31/XX |
|
6/14/XX |
|
|
|
Start of installation delayed to
allow two engineers to take early vacation. Completion should not
be delayed. |
| Third payment request: $40,000 |
|
6/07/XX |
|
|
|
|
|
|
| Mail Quarterly Performance Report |
|
7/17/XX |
|
|
|
|
|
|
| Transmitter testing begins |
|
7/26/XX |
|
|
|
|
|
|
| Transmitter installation completed |
|
8/18/XX |
|
|
|
|
|
|
| Final payment request: balance |
|
8/23/XX |
|
|
|
|
|
|
| Grant Award Period ends |
|
9/30/XX |
|
|
|
|
|
|
| Mail Quarterly Performance Report |
|
10/16/XX |
|
|
|
|
|
|
| Mail Close-Out |
|
12/15/XX |
|
|
|
|
|
|
Note: The March 4th flood took out
a bridge over Yellow Creek leading to the transmitter site. Truck delivery
of the new transmitter will be impossible until the bridge is repaired.
(Our engineers now have to walk the last mile to the transmitter.) We
are in contact with the Highway Department about the situation, and a
local National Guard Combat Construction Unit may be able to arrange delivery
by helicopter for us if necessary to complete the work on schedule.
Performance Report Summary:
Although there have been slight delays along the way,
the project is now essentially on schedule, and we have every expectation
that it will be completed by the end of the Grant Award Period. The situation
with the road to the transmitter site is serious and could result in a
project delay. There is still time for the road repairs, however, and
talks with the National Guard unit are very positive as to their being
able to help us-in fact, they appear eager to do so and hopeful that the
Highway Department will be unable to repair the road in time! If all this
ends by necessitating an extension of the Grant Award Period, we will
advise PTFP at least 30 days before the expiration date and formally request
an extension.
Equipment list is attached.
[signature]
Richard Who
Station Manager
| |
NOTE:
If you prepare your Report in hardcopy and do not have access to computer software and printers that type
landscape, use standard length paper and insert your remarks below
each Construction Schedule Activity in the Report. |
An example of the equipment list that accompanies
a Quarterly Performance Report follows in the link below.
You must submit a Financial Status Report
(SF-269 Long Form) for the six-month periods ending March 31 and September
30, or any portion thereof whether there was any financial activity
or not. The reports are due no later than April 30 and October
31, respectively. A final Financial Status Report must be submitted within
ninety days after the expiration of the Grant Award Period. If your PTFP
Grant Award Period began on October 1, your first Financial Status Report
is for the period ending March 31.
| NB: |
Financial Status Report forms are included in your award documents.
Completed reports should be sent to the National Institute of Standards and Technology (NIST), Grants and Agreements Management Division (GAMD), not to NTIA/PTFP. NIST/GAMD's address
is given under "Housekeeping Items." |
You must mark permanently all
equipment included in the project to ensure accurate identification and
accurate reference to inventory records.
A non-removable label (or other means of
identification) should be attached to the equipment where it can be seen
easily. The label should contain your organization's inventory number
plus the last five digits of the NTIA/PTFP grant award number.
Transmission antennas should be assigned
an inventory number. It should be posted in the transmitter shelter with
an appropriate identification.
Your organization has been awarded a PTFP grant to
purchase a specific number of specific items of equipment (or to do specific
planning) at an agreed-upon Total Project Cost. If the project can be
completed for less than the cost estimated in the award document, then
both your organization and the Federal government have saved money. (Funds
returned to PTFP in this way are awarded as grants in subsequent grant
rounds.)
After purchasing and installing all equipment on the
approved equipment list (or completing the approved planning activities)
you are NOT
authorized to spend any remaining Federal funds.
Similarly, if the approved equipment list includes
two Acme 1400's and they actually cost only half of what was expected,
you are NOT authorized to buy three or four as part of the grant project.
Amending an Award
Changes or additions can be made to the approved equipment
list (or planning activities) only with prior written
approval from the Department of Commerce through the National Telecommunications and Information Administration
(NTIA) from the Director of PTFP. No matter what anyone may say, if you do
not receive written approval, the request for an amendment has not
been approved.
Requests for amendments must be submitted in writing
to PTFP. The request should be clearly identified as an Amendment Request
and should not be combined with a Quarterly Performance Report,
an extension request, or any other submission. The request should
state clearly what changes you wish to make and the reasons for them.
All relevant cost figures must be included. NTIA suggests that you first
call your Program Officer and discuss the need for amending the grant
award.
Amendment requests will be reviewed by PTFP
prior to issuing written approval or denial. Amendments may be approved
if they are integral to, and within the scope of, the originally approved
project. Requests that would result in the expansion of the scope of the
project as granted usually will not be approved. Requests will
be reviewed to determine whether the amendment is the result of changes
in engineering approach, desire to implement new technology, or is necessary
for the operation of equipment originally approved in the grant.
Your written amendment request should contain
a statement along the following lines:
| |
The changes requested in this amendment
will be accomplished at no additional cost to the Federal government.
Any increase in the total cost of the project caused by the requested
amendment will be covered from local funding sources. |
| Or: |
|
| |
We have tentatively identified some funds within
the grant that may be available to help with this change, but we are
prepared to pay any increase in the total cost of the project from
local resources and the change will be accomplished at no additional
cost to the Federal government. |
When an Amendment Is Not Required
NTIA expects that, as a result of the competitive
bidding process, there will be differences in manufacturer and/or model
number in the equipment purchased versus the equipment approved in the award
document. There probably will also be some minor fluctuation in prices.
Amendments for these changes are not necessary as long as the equipment
purchased is equivalent in quantity and quality to what
appears in the award document equipment list. Please contact your Program
Officer if you have specific questions.
Unauthorized Expenditures
Equipment (or a planning activity) that does
not appear in the award document or has not been the subject of an approved
amendment will be removed from the project by NTIA/ PTFP at close-out. If
this occurs you may be required to refund Federal funds previously paid
to your organization.
The Grant Award Period is the time during
which your organization can obligate Federal funds to complete the approved
project. The Grant Award Period for your grant appears on the first page
of the award document. All Federal funds must be obligated and all equipment
must be installed and operational (or all planning activities completed)
by the end of the Grant Award Period.
Extensions may be granted for good cause.
Requests for extensions must be submitted in writing to PTFP. The request
should be clearly labeled as an Extension Request and should not
be combined with a Quarterly Performance Report, an amendment request,
or any other submission. An extension request should reach PTFP
at least three weeks before the end of the Grant Award Period. This will
allow your request to be given full consideration before the Grant Award
Period expires. Before submitting your request, NTIA suggests that you
call your Program Officer and discuss the need for extending the Grant
Award Period.
Your request should be supported by a full
explanation of what has happened to make an extension necessary. Generally
PTFP looks for causes beyond the grantee's control, such as failure of
a vendor to meet delivery dates, and it may request supporting documentation
(copies of correspondence, etc.) to accompany the request. It does not
look favorably on simple inactivity on the part of the grantee.
If you do not receive written
approval, the request for an extension has not been approved.
Extensions of the Award Period will usually be for
a minimum of three months and a maximum of one year.
|
A Note on Debts to the Department of Commerce
Please note that if your organization
has an outstanding bill from any part of the Department of Commerce
that is more than thirty days old, the National Institute of Standards and Technology (NIST), Grants and Agreements Management Division (GAMD) will not process an extension request until the debt
has been satisfied.
|
Non-profit organizations, government agencies,
Indian tribes, and educational institutions expending more than $500,000
in Federal funds from all sources during a one-year period are required
to have an audit conducted in accordance with Federal guidelines as stated
in OMB Circular A-133, dated June 30, 1997 (if you do not have a copy, you can get one by going to http://www.whitehouse.gov/omb and clicking on Circulars). These audits are performed in one of two ways. An
NTIA/PTFP-specific audit may be performed if the organization receives
Federal funds solely from NTIA. If the organization receives funds from
more than one Federal source during the year that the audit is conducted,
an organization-wide audit must be performed. (Note that CPB funding is
not considered a Federal source.)
In brief, OMB Circular A-133 requires that
all such recipients obtain regular audits, preferably annually, but at
least once every two years. Copies of the audits must be provided to each
Federal agency that provides funds to your organization. The copy of the
audit reports to be provided to the Department of Commerce should be sent
to the following address:
Mr. William F. Bedwell. Jr.
Office of Audits - Regional Audits
Office of Inspector General
U.S. Department of Commerce, Suite 2342
401 West Peachtree Street, NW
Atlanta, GA 30365
No matter which Federal agency
is officially to receive the audit, all PTFP grant recipients should
send a copy of the audit transmittal letter to their NIST/GAMD Grants
Specialist.
Audits performed in response to Corporation
for Public Broadcasting (CPB) qualification requirements will not necessarily
conform to the Federal government auditing standards required by Circular
A-133. The CPB requires a "standard" financial statement audit. While
such an audit will certainly serve as the basis for the A-133 audit, further
tests of the accounting records will have to be completed in order to
bring the audit into compliance with A-133. We urge you to review the
A-133 requirements with your accountant as early as possible.
| ** |
Grantees should review Section D
of the Department of Commerce Financial Assistance
Standard Terms and Conditions. Section D discusses audits. |
You are required to provide PTFP with full close-out
documentation for your project within ninety days following
project completion or the expiration of your Grant Award Period, whichever
comes first. As the closing date of your award approaches, you will receive
a reminder email from NTIA/PTFP. It will direct you to the Close-Out
Requirements section of this website, which contains complete instructions
to assist you in preparing your close-out. If you complete your project
early, you should proceed to that website without waiting for the reminder
because the 90-day close-out period starts when construction of your project
is completed and the equipment is operational.
It is essential that you maintain careful records
throughout the award period and that you respond promptly to the close-out
instructions so that you do not encounter unnecessary delays in preparing
your close-out materials.
Click here for complete Close-Out instructions and guidance.
Your responsibilities to the Federal government
through the Department of Commerce do not end when the National Institute of Standards and Technology (NIST), Grants and Agreements Management Division (GAMD) informs you that your close-out has been accepted. As you
know, the Federal government retains an interest in the equipment acquired as part
of the project for ten years after the close-out is completed. This section
summarizes some of the requirements; a full account of them appears in the
close-out part of this website.
Retention of Records
Grant recipients must keep intact and accessible
the following records:
| (1) |
|
A complete and itemized inventory
of all public telecommunications facilities under the control of
the grantee, whether or not financed, in whole or in part, with
Federal funds; |
| (2) |
|
Complete and current financial records
that fully disclose the total amount of the project; the amount
of the grant; the disposition of the grant proceeds; and the amount,
nature and source of non-Federal funds associated with the project;
and, |
| (3) |
|
All records specified in 15 CFR Part 14 (for educational institutions,
hospitals and nonprofit organizations) and 15 CFR Part 24 (for State
and Local Governments). |
Grantees must mark project apparatus in a permanent
manner in order to assure easy and accurate identification and reference to
inventory records. The marking shall include the PTFP grant number and a
unique inventory number assigned by the grantee.
Inspections
Grant recipients must permit inspections at any time during
normal working hours by NTIA and the Comptroller General of the United States,
or their duly authorized representatives, of the public telecommunications
facilities acquired with Federal financial assistance and of any books, documents, papers, and records relating to those facilities.
Annual Status Reports
Organizations that have received construction
grants from the Public Telecommunications Facilities Program (PTFP) are
required to submit an Annual Status Report for every grant project that
is in the Federal interest period. By statute, this is the 10-year period
during which the Federal government retains a reversionary interest in
all equipment purchased under the project. The Federal interest period
commences with the project completion date, as established by NTIA/PTFP
during the close-out procedure.
Annual Status Reports are due
on or before April 1 in each of the ten years of a grant's Federal interest
period. An organization must submit a separate Annual Status
Report--with an original signature--for each grant it has in the 10-year
Federal interest period.
Click here for more information about Annual Reports.
Recipients of Planning Grants are exempted
only from those requirements that relate narrowly to the acquisition
of equipment. Planning grantees, for example, do not have to submit
insurance and site rights certifications, liens, or FCC authorizations.
Nevertheless, Planning Grant recipients must meet many other requirements,
some of which are the same as those imposed on recipients of Construction
Grants.
Revised Planning
Schedule
The Planning Schedule is modeled on the Construction
Schedule, described above, except that the items listed relate to the
steps in the specific planning process, timetable, and activities required
to meet the objectives of the grant award.
Your grant application identified your project's
major objectives and procedures and provided a preliminary project timetable.
NTIA suggests that you reiterate and keep in mind the specific objectives
for your project as you revise and outline the planning process, timetable
to accomplish your project within the award period, step-by-step procedures,
and activities expected to be completed. You should contact your Program
Officer if you have questions regarding the Planning Schedule.
Quarterly Performance
Reports
The Quarterly Performance Reports should
follow the format described for Construction Grants above. Planning grant
recipients should provide updates and revisions to the timetable and activities
accomplished, brief summaries of meetings, copies of status reports regarding
the work of consultants, copies of planning studies, and so on.
Draft Final Report
Planning grant recipients are required
to submit a draft of the Final Report on their planning
project forty-five calendar days before the end of the
Grant Award Period for review by their Program Officer for consistency
with the goals and objectives, activities, Planning Schedule, and budget
of the project. The Program Officer will contact you with any NTIA suggestions
for revision or other comments intended to improve the quality of your
Final Report and help to ensure that it will be accepted.
Close-Out Requirements
You are required to provide full
close-out documentation to NTIA/PTFP within ninety days after project
completion or the expiration of your Grant Award Period, whichever comes
first. Click here for complete Close-Out instructions and guidance.
NOTICE |
|
We have estimated
that each response to this collection of information will take on
average 14 hours for construction grant recipients to prepare the
construction schedule and the quarterly performance reports and
54 hours for planning grant recipients to prepare the planning timetable,
the quarterly performance reports, and the draft final report. Our
estimates include the time to read the instructions, look through
existing records, gather and maintain required data, and actually
complete and review the response. If you have any comments on this
estimate or on how we can improve the collection and reduce the
burden it causes you, please write to the Office of Policy Coordination
and Management, NTIA, Room 4892, Department of Commerce, Washington,
DC 20230. Your comments will also be accepted via the Internet if
you send them to ptfp@ntia.doc.gov.
You are not required to respond to a collection of information sponsored
by the Federal government, and the government may not conduct or
sponsor this collection, unless it displays a currently valid OMB
control number or if we fail to provide you with this notice.
OMB Approval No. 0660-0001 Expires July 31, 2006
|